CPWD Analysis of Rates · Steel Work
Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters
80x1.20 mm M.S. laths with 1.20 mm thick top cover
- Item number
- 10.6.2
- Analysis basis
- Details of cost for a shutter of size 3mx-
- Priced inputs
- 9
- Derived rate
- ₹3,307.05 / a shutter
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.6.2 — Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters 80x1.20 mm M.S. laths with 1.20 mm thick top cover — is derived from 9 priced inputs for a shutter and works out to ₹3,307.05 per a shutter after water charges, GST, CPOH and cess. The full build-up is below.
- 2.5m = 7.5sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7045 | Rolling shutters of 80x1.2 mm lathsMaterial | sqm | 7.5 | 1,458.00 | 10,935.00 |
| 7047 | Top cover of Rolling shutters 1.20 mm thickMaterial | metre | 2.5 | 616.00 | 1,540.00 |
| 0975 | 27.5 cm long wire spring grade no 2 for rolling shutters27.5 cm long wire spring grade No. 2 for rolling shuttersMaterial | each | 1 | 330.00 | 330.00 |
| 9977 | CARRIAGEMaterial | L.S. | 53.82 | 2.27 | 122.17 |
| 0116 | Fitter (grade 1)Labour | day | 2.55 | 897.00 | 2,287.35 |
| 0114 | BeldarLabour | day | 2.55 | 736.00 | 1,876.80 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.12 | 897.00 | 107.64 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.12 | 816.00 | 97.92 |
| 9999 | SundriesMaterial | L.S. | 60.58 | 2.27 | 137.52 |
- TOTAL
- 17,434.40
- Add 1 % Water charges on “W”
- 174.34
- TOTAL
- 17,608.74
- Add GST on “X” (multiplying factor 0.2127)
- 3,745.38
- TOTAL
- 21,354.12
- Add 15% CPOH on “Y”
- 3,203.12
- TOTAL
- 24,557.24
- Add Cess @ 1% on “Z”
- 245.57
- Cost of 7.5sqm.
- 24,802.81
- Cost per sqm.
- 3,307.04
- Say
- 3,307.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 721. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.