CPWD Analysis of Rates · Steel Work

Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters

80x1.20 mm M.S. laths with 1.20 mm thick top cover

Item number
10.6.2
Analysis basis
Details of cost for a shutter of size 3mx-
Priced inputs
9
Derived rate
3,307.05 / a shutter

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.6.2 Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters 80x1.20 mm M.S. laths with 1.20 mm thick top cover — is derived from 9 priced inputs for a shutter and works out to ₹3,307.05 per a shutter after water charges, GST, CPOH and cess. The full build-up is below.

  • 2.5m = 7.5sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
7045Rolling shutters of 80x1.2 mm lathsMaterialsqm7.51,458.0010,935.00
7047Top cover of Rolling shutters 1.20 mm thickMaterialmetre2.5616.001,540.00
097527.5 cm long wire spring grade no 2 for rolling shutters27.5 cm long wire spring grade No. 2 for rolling shuttersMaterialeach1330.00330.00
9977CARRIAGEMaterialL.S.53.822.27122.17
0116Fitter (grade 1)Labourday2.55897.002,287.35
0114BeldarLabourday2.55736.001,876.80
0123Mason 1st classMason 1st classLabourday0.12897.00107.64
0124Mason 2nd classMason 2nd classLabourday0.12816.0097.92
9999SundriesMaterialL.S.60.582.27137.52
TOTAL
17,434.40
Add 1 % Water charges on “W”
174.34
TOTAL
17,608.74
Add GST on “X” (multiplying factor 0.2127)
3,745.38
TOTAL
21,354.12
Add 15% CPOH on “Y”
3,203.12
TOTAL
24,557.24
Add Cess @ 1% on “Z”
245.57
Cost of 7.5sqm.
24,802.81
Cost per sqm.
3,307.04
Say
3,307.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 721. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.