Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters

80x0.90 mm M.S. laths with 0.90 mm thick top cover
Item number
10.6.3
Analysis basis
a shutter
Priced inputs
9
Derived rate
₹3,191.35/ A SHUTTER
D-01/RATE ANALYSISITEM 10.6.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.6.3 (Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters 80x0.90 mm M.S. laths with 0.90 mm thick top cover) is derived from 9 priced inputs for a shutter and works out to ₹3,191.35 per a shutter after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 2.5m = 7.5sqm.
ANALYSIS OF RATES · ITEM 10.6.3DETAILS OF COST FOR A SHUTTER OF SIZE 3MX-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7044MATRolling shutters of 80x0.90 mm lathssqm7.51,417.0010,627.50
7046MATTop cover of Rolling shutters 0.90 mm thickmetre2.5495.001,237.50
0975MAT27.5 cm long wire spring grade no 2 for rolling shutters27.5 cm long wire spring grade No. 2 for rolling shutterseach1330.00330.00
9977MATCARRIAGEL.S.53.822.27122.17
0116LABFitter (grade 1)day2.55897.002,287.35
0114LABBeldarday2.55736.001,876.80
0123LABMason 1st classMason 1st classday0.12897.00107.64
0124LABMason 2nd classMason 2nd classday0.12816.0097.92
9999MATSundriesL.S.60.582.27137.52
BUILD-UP TO RATE
TOTAL
16,824.40
Add 1 % Water charges on “W”
+168.24
TOTAL
16,992.64
Add GST on “X” (multiplying factor 0.2127)
+3,614.33
TOTAL
20,606.97
Add 15% CPOH on “Y”
+3,091.05
TOTAL
23,698.02
Add Cess @ 1% on “Z”
+236.98
Cost of 7.5sqm.
23,935.00
Cost per sqm.
3,191.33
SAY
₹3,191.35
D-02/SOURCEPRINTED PAGE 722
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
722

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 722. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTEEL WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.