Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required

In stringers, treads, landings etc. of stair cases, including use of chequered plate wherever required, all complete
Item number
10.25.1
Analysis basis
5.331 quintal
Priced inputs
10
Derived rate
₹123.60/ QUINTAL
D-01/RATE ANALYSISITEM 10.25.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.25.1 (Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required In stringers, treads, landings etc. of stair cases, including use of chequered plate wherever required, all complete) is derived from 10 priced inputs for 5.331 quintal and works out to ₹123.60 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consider a flight of staircase of 2.8m height
  • with tread and riser of 200mm & 0.60m
  • wide.
  • (i) Unequal angles as stringers-75x50x6mm
  • 4x12.69x5.6 = 284.25 Kg.
  • Total = 298.46kg. Say 2.985q
  • (ii) unequal angles at sides -50x30x5mm
  • 2x14x0.2x3.00=16.8kg.
  • Total = 17.64 kg. Say 0.176q
  • Total = 3.161q
  • (iii) plate for tread 8mm thick
  • 14x7.5 = 105.00kg+
  • Total = 110.25kg. Say 1.103q
  • (iv) G.I. pipe for rolling 40mm
  • 2x12.69m = 25.38m+
  • Total = 26.65m
  • (v) M.S. round bars 16mm dia.
  • 15x0.75x2x1.58 = 35.55kg.+
  • Total = 37.33 Kg. Say 0.373q
  • 23.20 m = 2320cm
  • Applying priming coat
  • (i) steps 2.4x14 = 33.60sqm.+
  • (ii) angles-4x12.69x0.25 = 12.69sqm.+
  • (iii) Bars and other components =
  • 2.00 sqm. (L.S.)
  • Total = 48.29 sqm
  • Add wastage @ 5% = 14.21 Kg.
  • Add wastage @ 5% = 0.84kg.
  • Add wastage @ 5% = 5.25kg.
  • Add wastage @ 5% = 1.27m
  • Add wastage @ 5% = 1.78kg.
ANALYSIS OF RATES · ITEM 10.25.1DETAIL OF COST FOR 5.331 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1007MATStructurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsquintal3.1615,965.0018,855.37
1010MATMild steel platesquintal1.1035,700.006,287.10
1549MATG.I. pipes 40 mm diametre26.65290.007,728.50
1003MATMild steel round bar above 12 mm diaquintal0.3735,450.002,032.85
1215MATWelding by electric plantcm2,3202.505,800.00
0102LABBlacksmith 1st classday1.85897.001,659.45
0114LABBeldarday1.25736.00920.00
0100LABBandhaniday0.6816.00489.60
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm48.2967.403,254.75
9999MATSundriesL.S.110.892.27251.72
BUILD-UP TO RATE
TOTAL
47,279.34
Add 1 % Water charges on “W-A”
+440.25
TOTAL
47,719.59
Add GST on “X-A” (multiplying factor 0.2127)
+9,457.67
TOTAL
57,177.26
Add 15% CPOH on “Y-A”
+8,088.38
TOTAL
65,265.64
Add Cess @ 1% on “Z-A”
+620.11
Cost of 5.331 qunital
65,885.75
Cost per kg.
123.59
SAY
₹123.60
D-02/SOURCEPRINTED PAGE 741
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
741

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 741. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.