Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required
- Item number
- 10.25.1
- Analysis basis
- 5.331 quintal
- Priced inputs
- 10
- Derived rate
- ₹123.60/ QUINTAL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.25.1 (Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required In stringers, treads, landings etc. of stair cases, including use of chequered plate wherever required, all complete) is derived from 10 priced inputs for 5.331 quintal and works out to ₹123.60 per quintal after water charges, GST, CPOH and cess. The full build-up is below.
- Consider a flight of staircase of 2.8m height
- with tread and riser of 200mm & 0.60m
- wide.
- (i) Unequal angles as stringers-75x50x6mm
- 4x12.69x5.6 = 284.25 Kg.
- Total = 298.46kg. Say 2.985q
- (ii) unequal angles at sides -50x30x5mm
- 2x14x0.2x3.00=16.8kg.
- Total = 17.64 kg. Say 0.176q
- Total = 3.161q
- (iii) plate for tread 8mm thick
- 14x7.5 = 105.00kg+
- Total = 110.25kg. Say 1.103q
- (iv) G.I. pipe for rolling 40mm
- 2x12.69m = 25.38m+
- Total = 26.65m
- (v) M.S. round bars 16mm dia.
- 15x0.75x2x1.58 = 35.55kg.+
- Total = 37.33 Kg. Say 0.373q
- 23.20 m = 2320cm
- Applying priming coat
- (i) steps 2.4x14 = 33.60sqm.+
- (ii) angles-4x12.69x0.25 = 12.69sqm.+
- (iii) Bars and other components =
- 2.00 sqm. (L.S.)
- Total = 48.29 sqm
- Add wastage @ 5% = 14.21 Kg.
- Add wastage @ 5% = 0.84kg.
- Add wastage @ 5% = 5.25kg.
- Add wastage @ 5% = 1.27m
- Add wastage @ 5% = 1.78kg.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1007 | MAT | Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joists | quintal | 3.161 | 5,965.00 | 18,855.37 |
| 1010 | MAT | Mild steel plates | quintal | 1.103 | 5,700.00 | 6,287.10 |
| 1549 | MAT | G.I. pipes 40 mm dia | metre | 26.65 | 290.00 | 7,728.50 |
| 1003 | MAT | Mild steel round bar above 12 mm dia | quintal | 0.373 | 5,450.00 | 2,032.85 |
| 1215 | MAT | Welding by electric plant | cm | 2,320 | 2.50 | 5,800.00 |
| 0102 | LAB | Blacksmith 1st class | day | 1.85 | 897.00 | 1,659.45 |
| 0114 | LAB | Beldar | day | 1.25 | 736.00 | 920.00 |
| 0100 | LAB | Bandhani | day | 0.6 | 816.00 | 489.60 |
| SUB | Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3 | sqm | 48.29 | 67.40 | 3,254.75 | |
| 9999 | MAT | Sundries | L.S. | 110.89 | 2.27 | 251.72 |
- TOTAL
- 47,279.34
- Add 1 % Water charges on “W-A”
- +440.25
- TOTAL
- 47,719.59
- Add GST on “X-A” (multiplying factor 0.2127)
- +9,457.67
- TOTAL
- 57,177.26
- Add 15% CPOH on “Y-A”
- +8,088.38
- TOTAL
- 65,265.64
- Add Cess @ 1% on “Z-A”
- +620.11
- Cost of 5.331 qunital
- 65,885.75
- Cost per kg.
- 123.59
- SAY
- ₹123.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 741
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 741. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.