Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required

In stringers, treads, landings etc. of stair cases, including use of chequered plate wherever required, all complete

Item number
10.25.1
Analysis basis
Detail of cost for 5.331 quintal
Priced inputs
10
Derived rate
123.60 / quintal

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.25.1 Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required In stringers, treads, landings etc. of stair cases, including use of chequered plate wherever required, all complete — is derived from 10 priced inputs for 5.331 quintal and works out to ₹123.60 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

  • Consider a flight of staircase of 2.8m height
  • with tread and riser of 200mm & 0.60m
  • wide.
  • (i) Unequal angles as stringers-75x50x6mm
  • 4x12.69x5.6 = 284.25 Kg.
  • Total = 298.46kg. Say 2.985q
  • (ii) unequal angles at sides -50x30x5mm
  • 2x14x0.2x3.00=16.8kg.
  • Total = 17.64 kg. Say 0.176q
  • Total = 3.161q
  • (iii) plate for tread 8mm thick
  • 14x7.5 = 105.00kg+
  • Total = 110.25kg. Say 1.103q
  • (iv) G.I. pipe for rolling 40mm
  • 2x12.69m = 25.38m+
  • Total = 26.65m
  • (v) M.S. round bars 16mm dia.
  • 15x0.75x2x1.58 = 35.55kg.+
  • Total = 37.33 Kg. Say 0.373q
  • 23.20 m = 2320cm
  • Applying priming coat
  • (i) steps 2.4x14 = 33.60sqm.+
  • (ii) angles-4x12.69x0.25 = 12.69sqm.+
  • (iii) Bars and other components =
  • 2.00 sqm. (L.S.)
  • Total = 48.29 sqm
  • Add wastage @ 5% = 14.21 Kg.
  • Add wastage @ 5% = 0.84kg.
  • Add wastage @ 5% = 5.25kg.
  • Add wastage @ 5% = 1.27m
  • Add wastage @ 5% = 1.78kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
1007Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterialquintal3.1615,965.0018,855.37
1010Mild steel platesMaterialquintal1.1035,700.006,287.10
1549G.I. pipes 40 mm diaMaterialmetre26.65290.007,728.50
1003Mild steel round bar above 12 mm diaMaterialquintal0.3735,450.002,032.85
1215Welding by electric plantMaterialcm2,3202.505,800.00
0102Blacksmith 1st classLabourday1.85897.001,659.45
0114BeldarLabourday1.25736.00920.00
0100BandhaniLabourday0.6816.00489.60
Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysissqm48.2967.403,254.75
9999SundriesMaterialL.S.110.892.27251.72
TOTAL
47,279.34
Add 1 % Water charges on “W-A”
440.25
TOTAL
47,719.59
Add GST on “X-A” (multiplying factor 0.2127)
9,457.67
TOTAL
57,177.26
Add 15% CPOH on “Y-A”
8,088.38
TOTAL
65,265.64
Add Cess @ 1% on “Z-A”
620.11
Cost of 5.331 qunital
65,885.75
Cost per kg.
123.59
Say
123.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 741. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works