CPWD Analysis of Rates · Steel Work
Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required
In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
- Item number
- 10.25.2
- Priced inputs
- 8
- Derived rate
- ₹172.60
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.25.2 — Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works — is derived from 8 priced inputs and works out to ₹172.60 after water charges, GST, CPOH and cess. The full build-up is below.
- Details of 1mx1m framed guard bar grating
- (0.218 quintal).
- (i) M.S. flat 50x6mm 2.4kg/per metre
- 5.75x2.40 = 13.8kg.+
- Total = 14.49kg. Say 14.5 kg.
- (ii) 12mm dia. bars @ 0.89 kg/m
- 9x1= 9metre @ 0.89kg/m = 8.01kg+
- Total = 8.41 kg. Say 0.084q
- Applying priming coat 0.6 sqm.
- Add wastage @ 5% = 0.69kg.
- Add wastage @ 5% = 0.40kg.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1008 | Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterial | quintal | 0.145 | 5,450.00 | 790.25 |
| 1002 | Mild steel round bar 12 mm dia and belowMaterial | quintal | 0.084 | 5,550.00 | 466.20 |
| 1215 | Welding by electric plant 60 cmWelding by electric plantMaterial | cm | 60 | 2.50 | 150.00 |
| 0102 | Blacksmith 1st classLabour | day | 0.7 | 897.00 | 627.90 |
| 0114 | BeldarLabour | day | 0.5 | 736.00 | 368.00 |
| 0100 | BandhaniLabour | day | 0.25 | 816.00 | 204.00 |
| Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysis | sqm | 0.6 | 67.40 | 40.44 | |
| 9999 | SundriesMaterial | L.S. | 4.55 | 2.27 | 10.33 |
- TOTAL
- 2,657.12
- Add 1 % Water charges on “W-A”
- 26.17
- TOTAL
- 2,683.29
- Add GST on “X-A” (multiplying factor 0.2127)
- 562.13
- TOTAL
- 3,245.42
- Add 15% CPOH on “Y-A”
- 480.75
- TOTAL
- 3,726.17
- Add Cess @ 1% on “Z-A”
- 36.86
- Cost of 0.218 qunital
- 3,763.03
- Cost per kg
- 172.62
- Say
- 172.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 743. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works