Skip to main content
R/DAR 2023

Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required

In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
Item number
10.25.2
Priced inputs
8
Derived rate
₹172.60
D-01/RATE ANALYSISITEM 10.25.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.25.2 (Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works) is derived from 8 priced inputs and works out to ₹172.60 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Details of 1mx1m framed guard bar grating
  • (0.218 quintal).
  • (i) M.S. flat 50x6mm 2.4kg/per metre
  • 5.75x2.40 = 13.8kg.+
  • Total = 14.49kg. Say 14.5 kg.
  • (ii) 12mm dia. bars @ 0.89 kg/m
  • 9x1= 9metre @ 0.89kg/m = 8.01kg+
  • Total = 8.41 kg. Say 0.084q
  • Applying priming coat 0.6 sqm.
  • Add wastage @ 5% = 0.69kg.
  • Add wastage @ 5% = 0.40kg.
ANALYSIS OF RATES · ITEM 10.25.2
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1008MATFlats upto 10 mm in thicknessFlats up to 10 mm in thicknessquintal0.1455,450.00790.25
1002MATMild steel round bar 12 mm dia and belowquintal0.0845,550.00466.20
1215MATWelding by electric plant 60 cmWelding by electric plantcm602.50150.00
0102LABBlacksmith 1st classday0.7897.00627.90
0114LABBeldarday0.5736.00368.00
0100LABBandhaniday0.25816.00204.00
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm0.667.4040.44
9999MATSundriesL.S.4.552.2710.33
BUILD-UP TO RATE
TOTAL
2,657.12
Add 1 % Water charges on “W-A”
+26.17
TOTAL
2,683.29
Add GST on “X-A” (multiplying factor 0.2127)
+562.13
TOTAL
3,245.42
Add 15% CPOH on “Y-A”
+480.75
TOTAL
3,726.17
Add Cess @ 1% on “Z-A”
+36.86
Cost of 0.218 qunital
3,763.03
Cost per kg
172.62
SAY
₹172.60
D-02/SOURCEPRINTED PAGE 743
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
743

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 743. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTEEL WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.