Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required
- Item number
- 10.25.2
- Priced inputs
- 8
- Derived rate
- ₹172.60
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.25.2 (Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works) is derived from 8 priced inputs and works out to ₹172.60 after water charges, GST, CPOH and cess. The full build-up is below.
- Details of 1mx1m framed guard bar grating
- (0.218 quintal).
- (i) M.S. flat 50x6mm 2.4kg/per metre
- 5.75x2.40 = 13.8kg.+
- Total = 14.49kg. Say 14.5 kg.
- (ii) 12mm dia. bars @ 0.89 kg/m
- 9x1= 9metre @ 0.89kg/m = 8.01kg+
- Total = 8.41 kg. Say 0.084q
- Applying priming coat 0.6 sqm.
- Add wastage @ 5% = 0.69kg.
- Add wastage @ 5% = 0.40kg.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1008 | MAT | Flats upto 10 mm in thicknessFlats up to 10 mm in thickness | quintal | 0.145 | 5,450.00 | 790.25 |
| 1002 | MAT | Mild steel round bar 12 mm dia and below | quintal | 0.084 | 5,550.00 | 466.20 |
| 1215 | MAT | Welding by electric plant 60 cmWelding by electric plant | cm | 60 | 2.50 | 150.00 |
| 0102 | LAB | Blacksmith 1st class | day | 0.7 | 897.00 | 627.90 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 0100 | LAB | Bandhani | day | 0.25 | 816.00 | 204.00 |
| SUB | Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3 | sqm | 0.6 | 67.40 | 40.44 | |
| 9999 | MAT | Sundries | L.S. | 4.55 | 2.27 | 10.33 |
- TOTAL
- 2,657.12
- Add 1 % Water charges on “W-A”
- +26.17
- TOTAL
- 2,683.29
- Add GST on “X-A” (multiplying factor 0.2127)
- +562.13
- TOTAL
- 3,245.42
- Add 15% CPOH on “Y-A”
- +480.75
- TOTAL
- 3,726.17
- Add Cess @ 1% on “Z-A”
- +36.86
- Cost of 0.218 qunital
- 3,763.03
- Cost per kg
- 172.62
- SAY
- ₹172.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 743
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 743. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.