CPWD Analysis of Rates · Steel Work

Welding by gas or electric plant including transportation of plant at site etc. complete

Item number
10.22
Analysis basis
Details of cost for one cm.
Priced inputs
2
Derived rate
3.70 / one cm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.22 Welding by gas or electric plant including transportation of plant at site etc. complete — is derived from 2 priced inputs for one cm and works out to ₹3.70 per one cm after water charges, GST, CPOH and cess. The full build-up is below.

  • including transportation of welding plant at
  • site etc. complete
CodeInputUnitQuantityRate (INR)Amount (INR)
1214Welding by gas plantMaterialcm12.002.00
9999SundriesMaterialL.S.0.262.270.59
TOTAL
2.59
Add 1 % Water charges on “W”
0.03
TOTAL
2.62
Add GST on “X” (multiplying factor 0.2127)
0.56
TOTAL
3.18
Add 15% CPOH on “Y”
0.48
TOTAL
3.66
Add Cess @ 1% on “Z”
0.04
Cost of 1cm.
3.70
Say
3.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 741. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works