Welding by gas or electric plant including transportation of plant at site etc. complete
- Item number
- 10.22
- Analysis basis
- one cm
- Priced inputs
- 2
- Derived rate
- ₹3.70/ ONE CM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.22 (Welding by gas or electric plant including transportation of plant at site etc. complete) is derived from 2 priced inputs for one cm and works out to ₹3.70 per one cm after water charges, GST, CPOH and cess. The full build-up is below.
- including transportation of welding plant at
- site etc. complete
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1214 | MAT | Welding by gas plant | cm | 1 | 2.00 | 2.00 |
| 9999 | MAT | Sundries | L.S. | 0.26 | 2.27 | 0.59 |
- TOTAL
- 2.59
- Add 1 % Water charges on “W”
- +0.03
- TOTAL
- 2.62
- Add GST on “X” (multiplying factor 0.2127)
- +0.56
- TOTAL
- 3.18
- Add 15% CPOH on “Y”
- +0.48
- TOTAL
- 3.66
- Add Cess @ 1% on “Z”
- +0.04
- Cost of 1cm.
- 3.70
- SAY
- ₹3.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 741
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 741. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.