R/DAR 2023

Welding by gas or electric plant including transportation of plant at site etc. complete

Item number
10.22
Analysis basis
one cm
Priced inputs
2
Derived rate
₹3.70/ ONE CM
D-01/RATE ANALYSISITEM 10.22

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.22 (Welding by gas or electric plant including transportation of plant at site etc. complete) is derived from 2 priced inputs for one cm and works out to ₹3.70 per one cm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • including transportation of welding plant at
  • site etc. complete
ANALYSIS OF RATES · ITEM 10.22DETAILS OF COST FOR ONE CM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1214MATWelding by gas plantcm12.002.00
9999MATSundriesL.S.0.262.270.59
BUILD-UP TO RATE
TOTAL
2.59
Add 1 % Water charges on “W”
+0.03
TOTAL
2.62
Add GST on “X” (multiplying factor 0.2127)
+0.56
TOTAL
3.18
Add 15% CPOH on “Y”
+0.48
TOTAL
3.66
Add Cess @ 1% on “Z”
+0.04
Cost of 1cm.
3.70
SAY
₹3.70
D-02/SOURCEPRINTED PAGE 741
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
741

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 741. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTEEL WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.