CPWD Analysis of Rates · Steel Work
Providing and fixing M.S. rivets of sizes in position
- Item number
- 10.21
- Analysis basis
- Details of cost for 0.10q of rivets
- Priced inputs
- 4
- Derived rate
- ₹278.30 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.21 — Providing and fixing M.S. rivets of sizes in position — is derived from 4 priced inputs for 0.10q of and works out to ₹278.30 per kg after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1020 | Mild steel rivetsMaterial | quintal | 0.1 | 5,100.00 | 510.00 |
| 0116 | Fitter (grade 1)Labour | day | 0.83 | 897.00 | 744.51 |
| 0139 | Skilled Beldar (for floor rubbing etc.)Labour | day | 0.83 | 816.00 | 677.28 |
| 9999 | SundriesMaterial | L.S. | 10.79 | 2.27 | 24.49 |
- TOTAL
- 1,956.28
- Add 1 % Water charges on “W”
- 19.56
- TOTAL
- 1,975.84
- Add GST on “X” (multiplying factor 0.2127)
- 420.26
- TOTAL
- 2,396.10
- Add 15% CPOH on “Y”
- 359.42
- TOTAL
- 2,755.52
- Add Cess @ 1% on “Z”
- 27.56
- Cost of 0.10q
- 2,783.08
- Cost of 1 kg.
- 278.31
- Say
- 278.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 740. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.