Skip to main content

CPWD Analysis of Rates · Steel Work

Providing and fixing M.S. rivets of sizes in position

Item number
10.21
Analysis basis
Details of cost for 0.10q of rivets
Priced inputs
4
Derived rate
278.30 / kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.21 Providing and fixing M.S. rivets of sizes in position — is derived from 4 priced inputs for 0.10q of and works out to ₹278.30 per kg after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1020Mild steel rivetsMaterialquintal0.15,100.00510.00
0116Fitter (grade 1)Labourday0.83897.00744.51
0139Skilled Beldar (for floor rubbing etc.)Labourday0.83816.00677.28
9999SundriesMaterialL.S.10.792.2724.49
TOTAL
1,956.28
Add 1 % Water charges on “W”
19.56
TOTAL
1,975.84
Add GST on “X” (multiplying factor 0.2127)
420.26
TOTAL
2,396.10
Add 15% CPOH on “Y”
359.42
TOTAL
2,755.52
Add Cess @ 1% on “Z”
27.56
Cost of 0.10q
2,783.08
Cost of 1 kg.
278.31
Say
278.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 740. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works