Skip to main content
R/DAR 2023

Providing and fixing M.S. rivets of sizes in position

Item number
10.21
Analysis basis
0.10q of
Priced inputs
4
Derived rate
₹278.30/ KG
D-01/RATE ANALYSISITEM 10.21

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.21 (Providing and fixing M.S. rivets of sizes in position) is derived from 4 priced inputs for 0.10q of and works out to ₹278.30 per kg after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 10.21DETAILS OF COST FOR 0.10Q OF RIVETS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1020MATMild steel rivetsquintal0.15,100.00510.00
0116LABFitter (grade 1)day0.83897.00744.51
0139LABSkilled Beldar (for floor rubbing etc.)day0.83816.00677.28
9999MATSundriesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
1,956.28
Add 1 % Water charges on “W”
+19.56
TOTAL
1,975.84
Add GST on “X” (multiplying factor 0.2127)
+420.26
TOTAL
2,396.10
Add 15% CPOH on “Y”
+359.42
TOTAL
2,755.52
Add Cess @ 1% on “Z”
+27.56
Cost of 0.10q
2,783.08
Cost of 1 kg.
278.31
SAY
₹278.30
D-02/SOURCEPRINTED PAGE 740
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
740

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 740. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTEEL WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.