CPWD Analysis of Rates · Steel Work
Providing and fixing bolts including nuts and washers complete
- Item number
- 10.20
- Analysis basis
- Details of cost for 0.10q of nuts and washers
- Priced inputs
- 4
- Derived rate
- ₹159.35 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.20 — Providing and fixing bolts including nuts and washers complete — is derived from 4 priced inputs for 0.10q of and works out to ₹159.35 per kg after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1034 | Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthMaterial | quintal | 0.1 | 5,200.00 | 520.00 |
| 0103 | Blacksmith 2nd classLabour | day | 0.38 | 816.00 | 310.08 |
| 0114 | BeldarLabour | day | 0.38 | 736.00 | 279.68 |
| 9999 | SundriesMaterial | L.S. | 4.55 | 2.27 | 10.33 |
- TOTAL
- 1,120.09
- Add 1 % Water charges on “W”
- 11.20
- TOTAL
- 1,131.29
- Add GST on “X” (multiplying factor 0.2127)
- 240.63
- TOTAL
- 1,371.92
- Add 15% CPOH on “Y”
- 205.79
- TOTAL
- 1,577.71
- Add Cess @ 1% on “Z”
- 15.78
- Cost of 0.10q
- 1,593.49
- Cost of 1 kg.
- 159.35
- Say
- 159.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 740. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works