Providing and fixing mild steel round holding down bolts with nuts and washer plates complete
- Item number
- 10.19
- Analysis basis
- one bolt
- Priced inputs
- 4
- Derived rate
- ₹97.20/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.19 (Providing and fixing mild steel round holding down bolts with nuts and washer plates complete) is derived from 4 priced inputs for one bolt and works out to ₹97.20 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- 1200mm long (0.024 quital)
- l .2m @ 1.58kg/m = 1.895 kg = 0.019q
- Plate-100x100x6mm @ 47kg/sqm.
- Wt. = 0.47kg. = 0.005q
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1035 | MAT | Bolts and nuts above 300 mm in length | quintal | 0.019 | 5,300.00 | 100.70 |
| 1010 | MAT | Mild steel plates | quintal | 0.005 | 5,700.00 | 28.50 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.03 | 816.00 | 24.48 |
| 9988 | MAT | Carriage and labour for fixing | L.S. | 4.55 | 2.27 | 10.33 |
- TOTAL
- 164.01
- Add 1 % Water charges on “W”
- +1.64
- TOTAL
- 165.65
- Add GST on “X” (multiplying factor 0.2127)
- +35.23
- TOTAL
- 200.88
- Add 15% CPOH on “Y”
- +30.13
- TOTAL
- 231.01
- Add Cess @ 1% on “Z”
- +2.31
- Cost of 0.024q
- 233.32
- Cost of 1 kg.
- 97.22
- SAY
- ₹97.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 740
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 740. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.