CPWD Analysis of Rates · Steel Work

Providing and fixing circular/ Hexagonal cast iron or M.S. sheet box for ceiling fan clamp, of internal dia 140 mm, 73 mm height, top lid of 1.5 mm thick M.S. sheet with its top surface hacked for proper bonding, top lid shall be screwed into the cast iron/ M.S. sheet box by means of 3.3 mm dia round headed screws, one lock at the corners. Clamp shall be made of 12 mm dia M.S. bar bent to shape as per standard drawing

Item number
10.18
Analysis basis
Details of cost of one box clamp
Priced inputs
5
Derived rate
220.65

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.18 Providing and fixing circular/ Hexagonal cast iron or M.S. sheet box for ceiling fan clamp, of internal dia 140 mm, 73 mm height, top lid of 1.5 mm thick M.S. sheet with its top surface hacked for proper bonding, top lid shall be screwed into the cast iron/ M.S. sheet box by means of 3.3 mm dia round headed screws, one lock at the corners. Clamp shall be made of 12 mm dia M.S. bar bent to shape as per standard drawing — is derived from 5 priced inputs and works out to ₹220.65 after water charges, GST, CPOH and cess. The full build-up is below.

  • 12mm dia. M.S. bar 80cm @
  • 0.9kg/m = 0.72kg+
  • Total = 0.756 kg. Say 0.008 q
  • Add wastage @ 5% = 0.036
CodeInputUnitQuantityRate (INR)Amount (INR)
4012Circular C.I. Box for ceiling fanCircular C.I. Box for ceiling fan internal dia 140 mm, 73 mm height, toplid of 1.5 mm thick MS sheetMaterialeach160.0060.00
1002Mild steel round bar 12 mm dia and belowMaterialquintal0.0085,550.0044.40
0103Blacksmith 2nd classLabourday0.03816.0024.48
0114BeldarLabourday0.03736.0022.08
9988Sundries (Carriage, fixing and painting etc.)MaterialL.S.1.822.274.13
TOTAL
155.09
Add 1 % Water charges on “W”
1.55
TOTAL
156.64
Add GST on “X” (multiplying factor 0.2127)
33.32
TOTAL
189.96
Add 15% CPOH on “Y”
28.49
TOTAL
218.45
Add Cess @ 1% on “Z”
2.18
Cost for 1 box clamp
220.63
Say
220.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 739. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.