Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar, bent to shape with hooked ends in R.C.C. slabs or beams during laying, including painting the exposed portion of loop, all as per standard design complete
- Item number
- 10.17
- Analysis basis
- 1 clamp
- Priced inputs
- 4
- Derived rate
- ₹226.00/ CLAMP
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.17 (Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar, bent to shape with hooked ends in R.C.C. slabs or beams during laying, including painting the exposed portion of loop, all as per standard design complete) is derived from 4 priced inputs for 1 clamp and works out to ₹226.00 per clamp after water charges, GST, CPOH and cess. The full build-up is below.
- 16mm dia. M.S. bar 1m @ 1.58 kg/m
- 1x1.58 = 1.58Kg+
- Total = 1.66 Kg.
- Add wastage @ 5% = 0.08 Kg.
- Say 1.70kg. or 0.017q
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1003 | MAT | Mild steel round bar above 12 mm dia | quintal | 0.017 | 5,450.00 | 92.65 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.04 | 816.00 | 32.64 |
| 0114 | LAB | Beldar | day | 0.04 | 736.00 | 29.44 |
| 9988 | MAT | Sundries (Carriage, fixing and painting etc.) | L.S. | 1.82 | 2.27 | 4.13 |
- TOTAL
- 158.86
- Add 1 % Water charges on “W”
- +1.59
- TOTAL
- 160.45
- Add GST on “X” (multiplying factor 0.2127)
- +34.13
- TOTAL
- 194.58
- Add 15% CPOH on “Y”
- +29.19
- TOTAL
- 223.77
- Add Cess @ 1% on “Z”
- +2.24
- Cost for 1 clamp
- 226.01
- SAY
- ₹226.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 738
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 738. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.