CPWD Analysis of Rates · Steel Work
Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar, bent to shape with hooked ends in R.C.C. slabs or beams during laying, including painting the exposed portion of loop, all as per standard design complete
- Item number
- 10.17
- Analysis basis
- Details of cost for 1 clamp
- Priced inputs
- 4
- Derived rate
- ₹226.00 / clamp
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.17 — Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar, bent to shape with hooked ends in R.C.C. slabs or beams during laying, including painting the exposed portion of loop, all as per standard design complete — is derived from 4 priced inputs for 1 clamp and works out to ₹226.00 per clamp after water charges, GST, CPOH and cess. The full build-up is below.
- 16mm dia. M.S. bar 1m @ 1.58 kg/m
- 1x1.58 = 1.58Kg+
- Total = 1.66 Kg.
- Add wastage @ 5% = 0.08 Kg.
- Say 1.70kg. or 0.017q
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1003 | Mild steel round bar above 12 mm diaMaterial | quintal | 0.017 | 5,450.00 | 92.65 |
| 0103 | Blacksmith 2nd classLabour | day | 0.04 | 816.00 | 32.64 |
| 0114 | BeldarLabour | day | 0.04 | 736.00 | 29.44 |
| 9988 | Sundries (Carriage, fixing and painting etc.)Material | L.S. | 1.82 | 2.27 | 4.13 |
- TOTAL
- 158.86
- Add 1 % Water charges on “W”
- 1.59
- TOTAL
- 160.45
- Add GST on “X” (multiplying factor 0.2127)
- 34.13
- TOTAL
- 194.58
- Add 15% CPOH on “Y”
- 29.19
- TOTAL
- 223.77
- Add Cess @ 1% on “Z”
- 2.24
- Cost for 1 clamp
- 226.01
- Say
- 226.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 738. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.