CPWD Analysis of Rates · Steel Work
Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
Electric resistance or induction butt welded tubes
- Item number
- 10.16.3
- Analysis basis
- Details of cost for a truss of span 8 metre
- Priced inputs
- 7
- Derived rate
- ₹194.40 / a truss
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.16.3 — Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete Electric resistance or induction butt welded tubes — is derived from 7 priced inputs for a truss and works out to ₹194.40 per a truss after water charges, GST, CPOH and cess. The full build-up is below.
- weight = 119 kg.
- 50mm dia. tube
- Tie beam-1x8.0m = 8.00m+
- Principal rafter 2x4.30m = 8.60m
- Total = 16.60m
- 16.60m @ 5.10kg./m = 84.66kg.
- 40mm dia. tube
- Members = 2(0.45+1.25+0.90+2.15)
- Total = 2x4.75=9.50m
- 9.50m @ 3.61kg/m = 34.60Kg.
- Total = 118.96kg.
- Total = 124.90Kg. say 125 kg
- Priming coat
- 50mm dia. tube 16.60x0.157m = 2.61sqm.
- 40mm dia. tube 9.50x0.125m = 1.19 sqm.
- Total = 3.80 sqm.
- Welding charges:Rafter:- 4x22/7x6.03 = 75.80cm.+
- Ties:- 2x22/7x6.03=37.90cm.+
- Members:- 2x4x2x22/7x4.83=242.87cm
- Total= 356.57cm say 357cm
- Add wastage @ 5% = 5.94Kg.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 4011 | Mild steel tubes electric resistant or induction butt weldedMaterial | gram | 125 | 72.00 | 9,000.00 |
| Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysis | sqm | 3.8 | 67.40 | 256.12 | |
| 1215 | Welding by electric plantMaterial | cm | 357 | 2.50 | 892.50 |
| 0102 | Blacksmith 1st classLabour | day | 1.5 | 897.00 | 1,345.50 |
| 0100 | BandhaniLabour | day | 0.75 | 816.00 | 612.00 |
| 0114 | BeldarLabour | day | 5.5 | 736.00 | 4,048.00 |
| 9999 | SundriesMaterial | L.S. | 80.73 | 2.27 | 183.26 |
- TOTAL
- 16,337.38
- Add 1 % Water charges on “W-A”
- 160.81
- TOTAL
- 16,498.19
- Add GST on “X-A” (multiplying factor 0.2127)
- 3,454.69
- TOTAL
- 19,952.88
- Add 15% CPOH on “Y-A”
- 2,954.51
- TOTAL
- 22,907.39
- Add Cess @ 1% on “Z-A”
- 226.51
- Cost for 119 Kg.
- 23,133.90
- Cost for 1 Kg.
- 194.40
- Say
- 194.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 737. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works