Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete

Electric resistance or induction butt welded tubes

Item number
10.16.3
Analysis basis
Details of cost for a truss of span 8 metre
Priced inputs
7
Derived rate
194.40 / a truss

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.16.3 Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete Electric resistance or induction butt welded tubes — is derived from 7 priced inputs for a truss and works out to ₹194.40 per a truss after water charges, GST, CPOH and cess. The full build-up is below.

  • weight = 119 kg.
  • 50mm dia. tube
  • Tie beam-1x8.0m = 8.00m+
  • Principal rafter 2x4.30m = 8.60m
  • Total = 16.60m
  • 16.60m @ 5.10kg./m = 84.66kg.
  • 40mm dia. tube
  • Members = 2(0.45+1.25+0.90+2.15)
  • Total = 2x4.75=9.50m
  • 9.50m @ 3.61kg/m = 34.60Kg.
  • Total = 118.96kg.
  • Total = 124.90Kg. say 125 kg
  • Priming coat
  • 50mm dia. tube 16.60x0.157m = 2.61sqm.
  • 40mm dia. tube 9.50x0.125m = 1.19 sqm.
  • Total = 3.80 sqm.
  • Welding charges:Rafter:- 4x22/7x6.03 = 75.80cm.+
  • Ties:- 2x22/7x6.03=37.90cm.+
  • Members:- 2x4x2x22/7x4.83=242.87cm
  • Total= 356.57cm say 357cm
  • Add wastage @ 5% = 5.94Kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
4011Mild steel tubes electric resistant or induction butt weldedMaterialgram12572.009,000.00
Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysissqm3.867.40256.12
1215Welding by electric plantMaterialcm3572.50892.50
0102Blacksmith 1st classLabourday1.5897.001,345.50
0100BandhaniLabourday0.75816.00612.00
0114BeldarLabourday5.5736.004,048.00
9999SundriesMaterialL.S.80.732.27183.26
TOTAL
16,337.38
Add 1 % Water charges on “W-A”
160.81
TOTAL
16,498.19
Add GST on “X-A” (multiplying factor 0.2127)
3,454.69
TOTAL
19,952.88
Add 15% CPOH on “Y-A”
2,954.51
TOTAL
22,907.39
Add Cess @ 1% on “Z-A”
226.51
Cost for 119 Kg.
23,133.90
Cost for 1 Kg.
194.40
Say
194.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 737. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.