Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete

Electric resistance or induction butt welded tubes
Item number
10.16.3
Analysis basis
a truss
Priced inputs
7
Derived rate
₹194.40/ A TRUSS
D-01/RATE ANALYSISITEM 10.16.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.16.3 (Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete Electric resistance or induction butt welded tubes) is derived from 7 priced inputs for a truss and works out to ₹194.40 per a truss after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • weight = 119 kg.
  • 50mm dia. tube
  • Tie beam-1x8.0m = 8.00m+
  • Principal rafter 2x4.30m = 8.60m
  • Total = 16.60m
  • 16.60m @ 5.10kg./m = 84.66kg.
  • 40mm dia. tube
  • Members = 2(0.45+1.25+0.90+2.15)
  • Total = 2x4.75=9.50m
  • 9.50m @ 3.61kg/m = 34.60Kg.
  • Total = 118.96kg.
  • Total = 124.90Kg. say 125 kg
  • Priming coat
  • 50mm dia. tube 16.60x0.157m = 2.61sqm.
  • 40mm dia. tube 9.50x0.125m = 1.19 sqm.
  • Total = 3.80 sqm.
  • Welding charges:Rafter:- 4x22/7x6.03 = 75.80cm.+
  • Ties:- 2x22/7x6.03=37.90cm.+
  • Members:- 2x4x2x22/7x4.83=242.87cm
  • Total= 356.57cm say 357cm
  • Add wastage @ 5% = 5.94Kg.
ANALYSIS OF RATES · ITEM 10.16.3DETAILS OF COST FOR A TRUSS OF SPAN 8 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
4011MATMild steel tubes electric resistant or induction butt weldedgram12572.009,000.00
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm3.867.40256.12
1215MATWelding by electric plantcm3572.50892.50
0102LABBlacksmith 1st classday1.5897.001,345.50
0100LABBandhaniday0.75816.00612.00
0114LABBeldarday5.5736.004,048.00
9999MATSundriesL.S.80.732.27183.26
BUILD-UP TO RATE
TOTAL
16,337.38
Add 1 % Water charges on “W-A”
+160.81
TOTAL
16,498.19
Add GST on “X-A” (multiplying factor 0.2127)
+3,454.69
TOTAL
19,952.88
Add 15% CPOH on “Y-A”
+2,954.51
TOTAL
22,907.39
Add Cess @ 1% on “Z-A”
+226.51
Cost for 119 Kg.
23,133.90
Cost for 1 Kg.
194.40
SAY
₹194.40
D-02/SOURCEPRINTED PAGE 737
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
737

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 737. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTEEL WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.