Skip to main content

CPWD Analysis of Rates · Steel Work

Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete

Hot finished seamless type tubes

Item number
10.16.2
Analysis basis
Details of cost for a truss of span 8 metre
Priced inputs
7
Derived rate
206.35 / a truss

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.16.2 Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete Hot finished seamless type tubes — is derived from 7 priced inputs for a truss and works out to ₹206.35 per a truss after water charges, GST, CPOH and cess. The full build-up is below.

  • weight = 119 kg.
  • 50mm dia. tube
  • Tie beam- 1 x 8.0m = 8.00m +
  • Principal rafter 2x4.30m = 8.60m = 16.60m
  • 16.60m @ 5.10kg./ m = 84.66 kg.
  • 40mm dia. tube
  • Members = 2(0.45+1.25+0.90+2.15)
  • Total= 2x 4.75 = 9.50m
  • 9.50m @ 3.61kg/m = 34.60kg.
  • Total = 118.96kg.
  • Total=124.90kg. say 125 kg
  • Priming coat
  • 50mm dia. tube 16.60x0.157m = 2.61sqm.
  • 40mm dia. tube 9.50x0.125m = 1.19 sqm.
  • Total = 3.80 sqm.
  • Welding charges:Rafter:- 4x22/7x6.03 = 75.80cm.+
  • Ties :- 2x22/7x6.03=37.90cm.+
  • Members :- 2x4x2x22/7x4.83 = 242.87cm
  • Total= 356.57 cm say 357 cm
  • Add wastage @ 5% = 5.94kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
4010Mild steel tubes hot finished seamless typeMaterialgram12580.0010,000.00
Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysissqm3.867.40256.12
1215Welding by electric plantMaterialcm3572.50892.50
0102Blacksmith 1st classLabourday1.5897.001,345.50
0100BandhaniLabourday0.75816.00612.00
0114BeldarLabourday5.5736.004,048.00
9999SundriesMaterialL.S.80.732.27183.26
TOTAL
17,337.38
Add 1 % Water charges on “W-A”
170.81
TOTAL
17,508.19
Add GST on “X-A” (multiplying factor 0.2127)
3,669.52
TOTAL
21,177.71
Add 15% CPOH on “Y-A”
3,138.24
TOTAL
24,315.95
Add Cess @ 1% on “Z-A”
240.60
Cost for 119 kg
24,556.55
Cost for 1 kg
206.36
Say
206.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 737. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works