Extra for providing and fixing steel beading of size 10 x 10 x 1.6 mm (box type), approved shape and section with screws instead of glazing clips and metal sash putty, in steel doors, windows, ventilators and composite units

Item number
10.12
Analysis basis
1 metre
Priced inputs
3
Derived rate
₹49.60/ METRE
D-01/RATE ANALYSISITEM 10.12

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.12 (Extra for providing and fixing steel beading of size 10 x 10 x 1.6 mm (box type), approved shape and section with screws instead of glazing clips and metal sash putty, in steel doors, windows, ventilators and composite units) is derived from 3 priced inputs for 1 metre and works out to ₹49.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • windows, Ventilators and composit units
ANALYSIS OF RATES · ITEM 10.12DETAIL OF COST FOR 1 METRE BEADING FOR DOORS,
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1143MATSteel beading size 10 x 10 x 1.6 mm (box type)Steel beading 10x10x1.6 mm (box type)metre127.0027.00
9999MATApplying priming coatL.S.0.462.271.04
9999MATFixing chargesL.S.3.012.276.83
BUILD-UP TO RATE
TOTAL
34.87
Add 1 % Water charges on “W”
+0.35
TOTAL
35.22
Add GST on “X” (multiplying factor 0.2127)
+7.49
TOTAL
42.71
Add 15% CPOH on “Y”
+6.41
TOTAL
49.12
Add Cess @ 1% on “Z”
+0.49
Cost of 1 metre
49.61
SAY
₹49.60
D-02/SOURCEPRINTED PAGE 727
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
727

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 727. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.