CPWD Analysis of Rates · Sanitary Installations
Providing and fixing white vitreous china battery based infrared sensor operated urinal of approx. size 610 x 390 x 370 mm having pre & post flushing with water (250 ml & 500 ml consumption), having water inlet from back side, including fixing to wall with suitable brackets all as per manufacturers specification and direction of Engineer-in-charge
- Item number
- 17.80
- Analysis basis
- Details of cost for one pan
- Priced inputs
- 4
- Derived rate
- ₹7,979.20 / one pan
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.80 — Providing and fixing white vitreous china battery based infrared sensor operated urinal of approx. size 610 x 390 x 370 mm having pre & post flushing with water (250 ml & 500 ml consumption), having water inlet from back side, including fixing to wall with suitable brackets all as per manufacturers specification and direction of Engineer-in-charge — is derived from 4 priced inputs for one pan and works out to ₹7,979.20 per one pan after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7076 | White Vetrious UrinalBattery based infrared sensor operated white Vitreous Urinal of aprox. size 610x390x370 mmMaterial | each | 1 | 4,770.00 | 4,770.00 |
| 9977 | Carriage of materialsMaterial | L.S. | 9.79 | 2.27 | 22.22 |
| 0116 | Fitter (grade 1)Labour | day | 0.5 | 897.00 | 448.50 |
| 0114 | BeldarLabour | day | 0.5 | 736.00 | 368.00 |
- TOTAL
- 5,608.72
- Add 1 % Water charges on “W”
- 56.09
- TOTAL
- 5,664.81
- Add GST on “X” (multiplying factor 0.2127)
- 1,204.91
- TOTAL
- 6,869.72
- Add 15% CPOH on “Y”
- 1,030.46
- TOTAL
- 7,900.18
- Add Cess @ 1% on “Z”
- 79.00
- Cost of each
- 7,979.18
- Say
- 7,979.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1390. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.