Providing & fixing white vitreous china water less urinal of size 600 x 330 x 315 mm having antibacterial /germs free ceramic surface, fixed with cartridge having debris catcher and hygiene seal

Item number
17.79
Analysis basis
one pan
Priced inputs
5
Derived rate
₹18,088.45/ ONE PAN
D-01/RATE ANALYSISITEM 17.79

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.79 (Providing & fixing white vitreous china water less urinal of size 600 x 330 x 315 mm having antibacterial /germs free ceramic surface, fixed with cartridge having debris catcher and hygiene seal) is derived from 5 priced inputs for one pan and works out to ₹18,088.45 per one pan after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.79DETAILS OF COST FOR ONE PAN
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7074MATWhite Vetrious China Waterless UrinalWhite Vetrious China Waterless Urinal of size 600x330x315 mmeach19,500.009,500.00
7075MATCistern with fittings for Waterless Urinaleach12,376.002,376.00
9977MATCarriage of materialsL.S.9.792.2722.22
0116LABFitter (grade 1)day0.5897.00448.50
0114LABBeldarday0.5736.00368.00
BUILD-UP TO RATE
TOTAL
12,714.72
Add 1 % Water charges on “W”
+127.15
TOTAL
12,841.87
Add GST on “X” (multiplying factor 0.2127)
+2,731.47
TOTAL
15,573.34
Add 15% CPOH on “Y”
+2,336.00
TOTAL
17,909.34
Add Cess @ 1% on “Z”
+179.09
Cost of each
18,088.43
SAY
₹18,088.45
D-02/SOURCEPRINTED PAGE 1390
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1390

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1390. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.