Providing & fixing white vitreous china water less urinal of size 600 x 330 x 315 mm having antibacterial /germs free ceramic surface, fixed with cartridge having debris catcher and hygiene seal
- Item number
- 17.79
- Analysis basis
- one pan
- Priced inputs
- 5
- Derived rate
- ₹18,088.45/ ONE PAN
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.79 (Providing & fixing white vitreous china water less urinal of size 600 x 330 x 315 mm having antibacterial /germs free ceramic surface, fixed with cartridge having debris catcher and hygiene seal) is derived from 5 priced inputs for one pan and works out to ₹18,088.45 per one pan after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7074 | MAT | White Vetrious China Waterless UrinalWhite Vetrious China Waterless Urinal of size 600x330x315 mm | each | 1 | 9,500.00 | 9,500.00 |
| 7075 | MAT | Cistern with fittings for Waterless Urinal | each | 1 | 2,376.00 | 2,376.00 |
| 9977 | MAT | Carriage of materials | L.S. | 9.79 | 2.27 | 22.22 |
| 0116 | LAB | Fitter (grade 1) | day | 0.5 | 897.00 | 448.50 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
- TOTAL
- 12,714.72
- Add 1 % Water charges on “W”
- +127.15
- TOTAL
- 12,841.87
- Add GST on “X” (multiplying factor 0.2127)
- +2,731.47
- TOTAL
- 15,573.34
- Add 15% CPOH on “Y”
- +2,336.00
- TOTAL
- 17,909.34
- Add Cess @ 1% on “Z”
- +179.09
- Cost of each
- 18,088.43
- SAY
- ₹18,088.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1390
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1390. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.