Providing and fixing white vitreous china extended wall mounting water closet of size 780x370x690 mm of approved shape including providing & fixing white vitreous china cistern with dual flush fitting, of flushing capacity 3 litre/ 6 litre (adjustable to 4 litre/ 8 litres), including seat cover, and cistern fittings, nuts, bolts and gasket etc complete

Item number
17.78
Analysis basis
Details of cost for one pan
Priced inputs
7
Derived rate
14,999.15 / one pan

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.78 Providing and fixing white vitreous china extended wall mounting water closet of size 780x370x690 mm of approved shape including providing & fixing white vitreous china cistern with dual flush fitting, of flushing capacity 3 litre/ 6 litre (adjustable to 4 litre/ 8 litres), including seat cover, and cistern fittings, nuts, bolts and gasket etc complete — is derived from 7 priced inputs for one pan and works out to ₹14,999.15 per one pan after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7072Wall mounted water closetWall mounted water closet of size 780 x 370x690 mmMaterialeach15,940.005,940.00
7073Adjustable Vetrious China Cistern with fittingsAdjustable Vitreous China Cistern with fittings of flushing capacity 3 litre/ 6 litre (adjustable to 4 litre/8 litre)Materialeach11,600.001,600.00
1875White plastic seat (solid)with lid C.P.brass hinges and rubber buffersWhite plastic seat (solid) with lid C.P. brass hinges and rubber buffersMaterialeach1451.00451.00
9977Carriage of materialsMaterialL.S.9.792.2722.22
0116Fitter (grade 1)Labourday1897.00897.00
0123Mason 1st classMason 1st classLabourday1897.00897.00
0114BeldarLabourday1736.00736.00
TOTAL
10,543.22
Add 1 % Water charges on “W”
105.43
TOTAL
10,648.65
Add GST on “X” (multiplying factor 0.2127)
2,264.97
TOTAL
12,913.62
Add 15% CPOH on “Y”
1,937.04
TOTAL
14,850.66
Add Cess @ 1% on “Z”
148.51
Cost of each
14,999.17
Say
14,999.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1389. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.