CPWD Analysis of Rates · Sanitary Installations
Providing and fixing floor mounted, white vitreous china single piece, double traps syphonic water closet of approved brand/make, shape, size and pattern including integrated white vitreous china cistern of capacity 10 litre with dual flushing system, including all fittings and fixtures with seat cover, cistern fittings, nuts, bolts and gasket etc including making connection with the existing P/S trap, complete in all respect as per directions of Engineer-in-Charge
- Item number
- 17.81
- Analysis basis
- Details of cost for 1 no.
- Priced inputs
- 5
- Derived rate
- ₹18,212.90 / no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.81 — Providing and fixing floor mounted, white vitreous china single piece, double traps syphonic water closet of approved brand/make, shape, size and pattern including integrated white vitreous china cistern of capacity 10 litre with dual flushing system, including all fittings and fixtures with seat cover, cistern fittings, nuts, bolts and gasket etc including making connection with the existing P/S trap, complete in all respect as per directions of Engineer-in-Charge — is derived from 5 priced inputs for 1 no and works out to ₹18,212.90 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1966 | Floor mounted, white vitreous china single piece, double traps syphonic water closet of approved brand/make, shape, size and pattern including integrated white vitreous china cistern of capacity 10 litre with dual flushing system including all fittings and fixtures with seat cover, cistern fittings, nuts, bolts and gasket etcFloor mounted white vitrous china double trap syphonic WC with 10 litre cistern and all fittings & fixtures,seat cover etcMaterial | each | 1 | 10,250.00 | 10,250.00 |
| 9977 | Carriage of materialMaterial | L.S. | 9.79 | 2.27 | 22.22 |
| 0116 | Fitter (grade 1)Labour | day | 1 | 897.00 | 897.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 0123 | Mason 1st classMason 1st classLabour | day | 1 | 897.00 | 897.00 |
- TOTAL
- 12,802.22
- Add 1 % Water charges on “W”
- 128.02
- TOTAL
- 12,930.24
- Add GST on “X” (multiplying factor 0.2127)
- 2,750.26
- TOTAL
- 15,680.50
- Add 15% CPOH on “Y”
- 2,352.08
- TOTAL
- 18,032.58
- Add Cess @ 1% on “Z”
- 180.33
- Cost of each
- 18,212.91
- Say
- 18,212.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1391. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.