CPWD Analysis of Rates · Sanitary Installations
Providing and fixing white vitreous china pedestal for wash basin completely recessed at the back for the reception of pipes and fittings
- Item number
- 17.8
- Analysis basis
- Details of cost for one pedestal
- Priced inputs
- 3
- Derived rate
- ₹1,683.35 / one pedestal
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.8 — Providing and fixing white vitreous china pedestal for wash basin completely recessed at the back for the reception of pipes and fittings — is derived from 3 priced inputs for one pedestal and works out to ₹1,683.35 per one pedestal after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1396 | Vitrous china pedestal for wash basinVitreous china pedestal for wash basinMaterial | each | 1 | 1,000.00 | 1,000.00 |
| 9999 | White cement mortarMaterial | L.S. | 40.3 | 2.27 | 91.48 |
| 9988 | Carriage of materials and fixing chargesMaterial | L.S. | 40.43 | 2.27 | 91.78 |
- TOTAL
- 1,183.26
- Add 1 % Water charges on “W”
- 11.83
- TOTAL
- 1,195.09
- Add GST on “X” (multiplying factor 0.2127)
- 254.20
- TOTAL
- 1,449.29
- Add 15% CPOH on “Y”
- 217.39
- TOTAL
- 1,666.68
- Add Cess @ 1% on “Z”
- 16.67
- Cost of each
- 1,683.35
- Say
- 1,683.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1301. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works