Providing and fixing white vitreous china pedestal for wash basin completely recessed at the back for the reception of pipes and fittings
- Item number
- 17.8
- Analysis basis
- one pedestal
- Priced inputs
- 3
- Derived rate
- ₹1,683.35/ ONE PEDESTAL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.8 (Providing and fixing white vitreous china pedestal for wash basin completely recessed at the back for the reception of pipes and fittings) is derived from 3 priced inputs for one pedestal and works out to ₹1,683.35 per one pedestal after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1396 | MAT | Vitrous china pedestal for wash basinVitreous china pedestal for wash basin | each | 1 | 1,000.00 | 1,000.00 |
| 9999 | MAT | White cement mortar | L.S. | 40.3 | 2.27 | 91.48 |
| 9988 | MAT | Carriage of materials and fixing charges | L.S. | 40.43 | 2.27 | 91.78 |
- TOTAL
- 1,183.26
- Add 1 % Water charges on “W”
- +11.83
- TOTAL
- 1,195.09
- Add GST on “X” (multiplying factor 0.2127)
- +254.20
- TOTAL
- 1,449.29
- Add 15% CPOH on “Y”
- +217.39
- TOTAL
- 1,666.68
- Add Cess @ 1% on “Z”
- +16.67
- Cost of each
- 1,683.35
- SAY
- ₹1,683.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1301
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1301. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.