Providing and fixing white vitreous china pedestal for wash basin completely recessed at the back for the reception of pipes and fittings

Item number
17.8
Analysis basis
one pedestal
Priced inputs
3
Derived rate
₹1,683.35/ ONE PEDESTAL
D-01/RATE ANALYSISITEM 17.8

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.8 (Providing and fixing white vitreous china pedestal for wash basin completely recessed at the back for the reception of pipes and fittings) is derived from 3 priced inputs for one pedestal and works out to ₹1,683.35 per one pedestal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.8DETAILS OF COST FOR ONE PEDESTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1396MATVitrous china pedestal for wash basinVitreous china pedestal for wash basineach11,000.001,000.00
9999MATWhite cement mortarL.S.40.32.2791.48
9988MATCarriage of materials and fixing chargesL.S.40.432.2791.78
BUILD-UP TO RATE
TOTAL
1,183.26
Add 1 % Water charges on “W”
+11.83
TOTAL
1,195.09
Add GST on “X” (multiplying factor 0.2127)
+254.20
TOTAL
1,449.29
Add 15% CPOH on “Y”
+217.39
TOTAL
1,666.68
Add Cess @ 1% on “Z”
+16.67
Cost of each
1,683.35
SAY
₹1,683.35
D-02/SOURCEPRINTED PAGE 1301
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1301

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1301. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.