CPWD Analysis of Rates · Sanitary Installations
Providing and fixing kitchen sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P. brass waste complete, including painting the fittings and brackets, cutting and making good the walls wherever required
White glazed fire clay kitchen sink of size 600x450x 250 mm
- Item number
- 17.9.1
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 11
- Derived rate
- ₹3,892.75 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.9.1 — Providing and fixing kitchen sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P. brass waste complete, including painting the fittings and brackets, cutting and making good the walls wherever required: White glazed fire clay kitchen sink of size 600x450x 250 mm — is derived from 11 priced inputs for one no and works out to ₹3,892.75 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1863 | Fire clay kitchen sink: 600x450x250 mmMaterial | each | 1 | 1,430.00 | 1,430.00 |
| 1309 | C.I. bracket for wash basin and sinksMaterial | pair | 1 | 95.00 | 95.00 |
| 1315 | C.P.brass chain with 40 mm dia rubber plugMaterial | each | 1 | 37.00 | 37.00 |
| 1952 | C.P. brass waste 40 mmMaterial | each | 1 | 110.00 | 110.00 |
| 9999 | Red lead, white lead and gaskitMaterial | L.S. | 16.12 | 2.27 | 36.59 |
| 9999 | Cement, sand and grit etc.Material | L.S. | 13.39 | 2.27 | 30.40 |
| 9999 | Painting brackets etc.Material | L.S. | 26.91 | 2.27 | 61.09 |
| 9977 | Carriage of materialsMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 0116 | Fitter (grade 1)Labour | day | 0.22 | 897.00 | 197.34 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.33 | 897.00 | 296.01 |
| 0114 | BeldarLabour | day | 0.56 | 736.00 | 412.16 |
- TOTAL
- 2,736.28
- Add 1 % Water charges on “W”
- 27.36
- TOTAL
- 2,763.64
- Add GST on “X” (multiplying factor 0.2127)
- 587.83
- TOTAL
- 3,351.47
- Add 15% CPOH on “Y”
- 502.72
- TOTAL
- 3,854.19
- Add Cess @ 1% on “Z”
- 38.54
- Cost of each
- 3,892.73
- Say
- 3,892.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1301. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.