Providing and fixing kitchen sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P. brass waste complete, including painting the fittings and brackets, cutting and making good the walls wherever required

White glazed fire clay kitchen sink of size 600x450x 250 mm
Item number
17.9.1
Analysis basis
one no
Priced inputs
11
Derived rate
₹3,892.75/ ONE NO
D-01/RATE ANALYSISITEM 17.9.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.9.1 (Providing and fixing kitchen sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P. brass waste complete, including painting the fittings and brackets, cutting and making good the walls wherever required: White glazed fire clay kitchen sink of size 600x450x 250 mm) is derived from 11 priced inputs for one no and works out to ₹3,892.75 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.9.1DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1863MATFire clay kitchen sink: 600x450x250 mmeach11,430.001,430.00
1309MATC.I. bracket for wash basin and sinkspair195.0095.00
1315MATC.P.brass chain with 40 mm dia rubber plugeach137.0037.00
1952MATC.P. brass waste 40 mmeach1110.00110.00
9999MATRed lead, white lead and gaskitL.S.16.122.2736.59
9999MATCement, sand and grit etc.L.S.13.392.2730.40
9999MATPainting brackets etc.L.S.26.912.2761.09
9977MATCarriage of materialsL.S.13.522.2730.69
0116LABFitter (grade 1)day0.22897.00197.34
0123LABMason 1st classMason 1st classday0.33897.00296.01
0114LABBeldarday0.56736.00412.16
BUILD-UP TO RATE
TOTAL
2,736.28
Add 1 % Water charges on “W”
+27.36
TOTAL
2,763.64
Add GST on “X” (multiplying factor 0.2127)
+587.83
TOTAL
3,351.47
Add 15% CPOH on “Y”
+502.72
TOTAL
3,854.19
Add Cess @ 1% on “Z”
+38.54
Cost of each
3,892.73
SAY
₹3,892.75
D-02/SOURCEPRINTED PAGE 1301
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1301

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1301. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.