CPWD Analysis of Rates · Sanitary Installations

Providing and fixing kitchen sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P. brass waste complete, including painting the fittings and brackets, cutting and making good the walls wherever required

White glazed fire clay kitchen sink of size 600x450x 250 mm

Item number
17.9.1
Analysis basis
Details of cost for one no.
Priced inputs
11
Derived rate
3,892.75 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.9.1 Providing and fixing kitchen sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm C.P. brass waste complete, including painting the fittings and brackets, cutting and making good the walls wherever required: White glazed fire clay kitchen sink of size 600x450x 250 mm — is derived from 11 priced inputs for one no and works out to ₹3,892.75 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1863Fire clay kitchen sink: 600x450x250 mmMaterialeach11,430.001,430.00
1309C.I. bracket for wash basin and sinksMaterialpair195.0095.00
1315C.P.brass chain with 40 mm dia rubber plugMaterialeach137.0037.00
1952C.P. brass waste 40 mmMaterialeach1110.00110.00
9999Red lead, white lead and gaskitMaterialL.S.16.122.2736.59
9999Cement, sand and grit etc.MaterialL.S.13.392.2730.40
9999Painting brackets etc.MaterialL.S.26.912.2761.09
9977Carriage of materialsMaterialL.S.13.522.2730.69
0116Fitter (grade 1)Labourday0.22897.00197.34
0123Mason 1st classMason 1st classLabourday0.33897.00296.01
0114BeldarLabourday0.56736.00412.16
TOTAL
2,736.28
Add 1 % Water charges on “W”
27.36
TOTAL
2,763.64
Add GST on “X” (multiplying factor 0.2127)
587.83
TOTAL
3,351.47
Add 15% CPOH on “Y”
502.72
TOTAL
3,854.19
Add Cess @ 1% on “Z”
38.54
Cost of each
3,892.73
Say
3,892.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1301. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.