Skip to main content

CPWD Analysis of Rates · Sanitary Installations

Providing and fixing wash basin with C.I. brackets, 15 mm dia CP Brass single hole basin mixer of approved quality and make, including painting of fittings and brackets, cutting and making good the walls wherever required:- (a) White Vitreous China Wash basin size 550x400 mm with a 15 mm CP Brass single hole basin mixer

Item number
17.7A
Analysis basis
Details of cost for 1 no.
Priced inputs
9
Derived rate
3,960.55 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.7A Providing and fixing wash basin with C.I. brackets, 15 mm dia CP Brass single hole basin mixer of approved quality and make, including painting of fittings and brackets, cutting and making good the walls wherever required:- (a) White Vitreous China Wash basin size 550x400 mm with a 15 mm CP Brass single hole basin mixer — is derived from 9 priced inputs for 1 no and works out to ₹3,960.55 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
3229Vitreous china flat back wash basin 550x400 mmMaterialeach1554.00554.00
9001C.P. Brass Centre Hole Basin Mixer With Cast Spout ( Kigston/Marc/Prima/ Parko/ Hindware)C.P. Brass Centre Hole Basin Mixer With Cast SpoutMaterialeach11,760.001,760.00
1951C.P. brass waste 32 mmMaterialeach194.0094.00
1309C.I. bracket for wash basin and sinksMaterialpair195.0095.00
9999Red lead, white lead and gaskitMaterialL.S.16.122.2736.59
9999Cement, Sand and grit etc.MaterialL.S.13.392.2730.40
9999Painting of brackets, fittings etc.MaterialL.S.26.912.2761.09
9977Carriage of materialsMaterialL.S.13.522.2730.69
9999Fixing ChargesMaterialL.S.53.822.27122.17
TOTAL
2,783.94
Add 1 % Water charges on “W”
27.84
TOTAL
2,811.78
Add GST on “X” (multiplying factor 0.2127)
598.07
TOTAL
3,409.85
Add 15% CPOH on “Y”
511.48
TOTAL
3,921.33
Add Cess @ 1% on “Z”
39.21
Cost of each
3,960.54
Say
3,960.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1299. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.