Skip to main content

CPWD Analysis of Rates · Sanitary Installations

Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require

Stainless Steel AISI-304(18/8) Wash basin 530x345 mm with single 15 mm C.P. brass pillar tap

Item number
17.7.11
Analysis basis
Details of cost for one no.
Priced inputs
9
Derived rate
4,149.75 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.7.11 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require: Stainless Steel AISI-304(18/8) Wash basin 530x345 mm with single 15 mm C.P. brass pillar tap — is derived from 9 priced inputs for one no and works out to ₹4,149.75 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7807Salem Stainless steel AISI - 304 (18/8) Wash basin 530mm X 345mmSalem Stainless steel AISI - 304 (18/8) Wash basin 530 mm X 345 mmMaterialeach12,150.002,150.00
188515 mm C.P.brass tap15 mm C.P. brass tapMaterialeach1297.00297.00
1951C.P. brass waste 32 mmMaterialeach194.0094.00
1309C.I. bracket for wash basin and sinksMaterialpair195.0095.00
9999Red lead, white lead and gaskitMaterialL.S.16.122.2736.59
9999Cement, sand and grit etc.MaterialL.S.13.392.2730.40
9999Painting of brackets, fittings etc.MaterialL.S.26.912.2761.09
9977Carriage of materialsMaterialL.S.13.522.2730.69
9999Fixing ChargesMaterialL.S.53.822.27122.17
TOTAL
2,916.94
Add 1 % Water charges on “W”
29.17
TOTAL
2,946.11
Add GST on “X” (multiplying factor 0.2127)
626.64
TOTAL
3,572.75
Add 15% CPOH on “Y”
535.91
TOTAL
4,108.66
Add Cess @ 1% on “Z”
41.09
Cost of each
4,149.75
Say
4,149.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1299. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works