Providing and fixing PTMT 15 mm Urinal spreader size 95x69x100 mm with 1/2” BSP thread and shapes, weighing not less than 60 gms

Item number
17.75
Analysis basis
Details of cost for one no.
Priced inputs
2
Derived rate
107.20 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.75 Providing and fixing PTMT 15 mm Urinal spreader size 95x69x100 mm with 1/2” BSP thread and shapes, weighing not less than 60 gms — is derived from 2 priced inputs for one no and works out to ₹107.20 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7508PTMT Urinal Spreader 15mmPTMT - Urinal Spreader 15 mmMaterialeach160.0060.00
9988Carriage of materials and fixing chargesMaterialL.S.6.762.2715.35
TOTAL
75.35
Add 1 % Water charges on “W”
0.75
TOTAL
76.10
Add GST on “X” (multiplying factor 0.2127)
16.19
TOTAL
92.29
Add 15% CPOH on “Y”
13.84
TOTAL
106.13
Add Cess @ 1% on “Z”
1.06
Cost of each
107.19
Say
107.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1385. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.