Providing and fixing PTMT 15 mm Urinal spreader size 95x69x100 mm with 1/2” BSP thread and shapes, weighing not less than 60 gms

Item number
17.75
Analysis basis
one no
Priced inputs
2
Derived rate
₹107.20/ ONE NO
D-01/RATE ANALYSISITEM 17.75

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.75 (Providing and fixing PTMT 15 mm Urinal spreader size 95x69x100 mm with 1/2” BSP thread and shapes, weighing not less than 60 gms) is derived from 2 priced inputs for one no and works out to ₹107.20 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.75DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7508MATPTMT Urinal Spreader 15mmPTMT - Urinal Spreader 15 mmeach160.0060.00
9988MATCarriage of materials and fixing chargesL.S.6.762.2715.35
BUILD-UP TO RATE
TOTAL
75.35
Add 1 % Water charges on “W”
+0.75
TOTAL
76.10
Add GST on “X” (multiplying factor 0.2127)
+16.19
TOTAL
92.29
Add 15% CPOH on “Y”
+13.84
TOTAL
106.13
Add Cess @ 1% on “Z”
+1.06
Cost of each
107.19
SAY
₹107.20
D-02/SOURCEPRINTED PAGE 1385
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1385

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1385. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS