CPWD Analysis of Rates · Sanitary Installations

Providing and fixing PTMT shelf 440 mm long, 124 mm width and 36 mm height of approved quality and colour, weighing not less than 300 gms

Item number
17.74
Analysis basis
Details of cost for one no.
Priced inputs
6
Derived rate
713.20 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.74 Providing and fixing PTMT shelf 440 mm long, 124 mm width and 36 mm height of approved quality and colour, weighing not less than 300 gms — is derived from 6 priced inputs for one no and works out to ₹713.20 per one no after water charges, GST, CPOH and cess. The full build-up is below.

  • Wooden cleates
CodeInputUnitQuantityRate (INR)Amount (INR)
7507PTMT Shelf 450x124x36mmPTMT Shelf 450x124x36 mmMaterialeach1160.00160.00
Rate as per item no 8.23 of SH : Cladding workRate as per item 8.23Sub-analysiseach240.8581.70
0588Chromium plated Brass screws 25 mmMaterial100 Nos0.06177.0010.62
9977Carriage of materialsMaterialL.S.4.162.279.44
0112Carpenter 2nd classLabourday0.17816.00138.72
0114BeldarLabourday0.17736.00125.12
TOTAL
525.60
Add 1 % Water charges on “W-A”
4.44
TOTAL
530.04
Add GST on “X-A” (multiplying factor 0.2127)
95.36
TOTAL
625.40
Add 15% CPOH on “Y-A”
81.56
TOTAL
706.96
Add Cess @ 1% on “Z-A”
6.25
Cost of each
713.21
Say
713.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1385. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.