Skip to main content
R/DAR 2023

Cutting chases in brick masonry walls for following diameter sand cast iron/centrifugally cast (spun) iron pipes and making good the same with cement concrete 1:3:6 (1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size), including necessary plaster and pointing in cement mortar 1:4 (1 cement : 4 coarse sand)

100 mm dia
Item number
17.61.1
Analysis basis
one metre
Priced inputs
5
Derived rate
₹713.20/ ONE METRE
D-01/RATE ANALYSISITEM 17.61.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.61.1 (Cutting chases in brick masonry walls for following diameter sand cast iron/centrifugally cast (spun) iron pipes and making good the same with cement concrete 1:3:6 (1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size), including necessary plaster and pointing in cement mortar 1:4 (1 cement : 4 coarse sand) : 100 mm dia) is derived from 5 priced inputs for one metre and works out to ₹713.20 per one metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:3:6 (1 cement : 3
  • coarse sand :6 graded stone aggregate )
ANALYSIS OF RATES · ITEM 17.61.1DETAILS OF COST FOR ONE METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5cum0.0229,311.40204.85
9999MATPlastering in cement mortar 1:4L.S.10.42.2723.61
9977MATCarriage of materialsL.S.4.162.279.44
0123LABMason 1st classMason 1st classday0.14897.00125.58
0114LABBeldarday0.27736.00198.72
BUILD-UP TO RATE
TOTAL
562.20
Add 1 % Water charges on “W-A”
+3.57
TOTAL
565.77
Add GST on “X-A” (multiplying factor 0.2127)
+76.77
TOTAL
642.54
Add 15% CPOH on “Y-A”
+65.65
TOTAL
708.19
Add Cess @ 1% on “Z-A”
+5.03
Cost of one metre
713.22
SAY
₹713.20
D-02/SOURCEPRINTED PAGE 1375
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1375

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1375. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.