CPWD Analysis of Rates · Sanitary Installations
Cutting chases in brick masonry walls for following diameter sand cast iron/centrifugally cast (spun) iron pipes and making good the same with cement concrete 1:3:6 (1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size), including necessary plaster and pointing in cement mortar 1:4 (1 cement : 4 coarse sand)
75 mm dia
- Item number
- 17.61.2
- Analysis basis
- Details of cost for one metre
- Priced inputs
- 5
- Derived rate
- ₹513.25 / one metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.61.2 — Cutting chases in brick masonry walls for following diameter sand cast iron/centrifugally cast (spun) iron pipes and making good the same with cement concrete 1:3:6 (1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size), including necessary plaster and pointing in cement mortar 1:4 (1 cement : 4 coarse sand) : 75 mm dia — is derived from 5 priced inputs for one metre and works out to ₹513.25 per one metre after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:3:6 (1 cement : 3
- coarse sand :6 graded stone aggregate )
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5Sub-analysis | cum | 0.015 | 9,311.40 | 139.67 | |
| 9999 | Plastering in cement mortar 1:4Material | L.S. | 7.8 | 2.27 | 17.71 |
| 9977 | Carriage of materialsMaterial | L.S. | 3.51 | 2.27 | 7.97 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.1 | 897.00 | 89.70 |
| 0114 | BeldarLabour | day | 0.2 | 736.00 | 147.20 |
- TOTAL
- 402.25
- Add 1 % Water charges on “W-A”
- 2.63
- TOTAL
- 404.88
- Add GST on “X-A” (multiplying factor 0.2127)
- 56.41
- TOTAL
- 461.29
- Add 15% CPOH on “Y-A”
- 48.24
- TOTAL
- 509.53
- Add Cess @ 1% on “Z-A”
- 3.70
- Cost of one metre
- 513.23
- Say
- 513.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1376. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.