Providing and fixing one piece construction white vitreous china squatting plate with an integral longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I. / PVC flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P. brass coupling complete, including painting of fittings and cutting and making good the walls and floors etc. wherever required

Range of two squatting plates with 5 litre P.V.C. automatic flushing cistern
Item number
17.6.2
Analysis basis
one no
Priced inputs
10
Derived rate
₹13,476.35/ ONE NO
D-01/RATE ANALYSISITEM 17.6.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.6.2 (Providing and fixing one piece construction white vitreous china squatting plate with an integral longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I. / PVC flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P. brass coupling complete, including painting of fittings and cutting and making good the walls and floors etc. wherever required : Range of two squatting plates with 5 litre P.V.C. automatic flushing cistern) is derived from 10 priced inputs for one no and works out to ₹13,476.35 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.6.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1915MATVitreous china squatting plate urinaleach21,158.002,316.00
7359MATP.V.C. automatic flushing cistern 5 lts capacityP.V.C. automatic flushing cistern 5 litre capacityeach1477.00477.00
1541MATFlush pipe and spreaders G.I.for range of two squatting plates urinalFlush pipe and spreaders G.l. for range of two squatting plates urinaleach1300.00300.00
9999MATRed lead, white lead and gaskitL.S.17.552.2739.84
9999MATCement, sand and grit etc.L.S.53.822.27122.17
9999MATPainting of fittings etc.L.S.262.2759.02
9977MATCarriage of materialsL.S.33.152.2775.25
0116LABFitter (grade 1)day2.5897.002,242.50
0123LABMason 1st classMason 1st classday1897.00897.00
0114LABBeldarday4736.002,944.00
BUILD-UP TO RATE
TOTAL
9,472.78
Add 1 % Water charges on “W”
+94.73
TOTAL
9,567.51
Add GST on “X” (multiplying factor 0.2127)
+2,035.01
TOTAL
11,602.52
Add 15% CPOH on “Y”
+1,740.38
TOTAL
13,342.90
Add Cess @ 1% on “Z”
+133.43
Cost of each
13,476.33
SAY
₹13,476.35
D-02/SOURCEPRINTED PAGE 1291
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1291

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1291. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.