Providing and fixing one piece construction white vitreous china squatting plate with an integral longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I. / PVC flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P. brass coupling complete, including painting of fittings and cutting and making good the walls and floors etc. wherever required
- Item number
- 17.6.3
- Analysis basis
- one no
- Priced inputs
- 10
- Derived rate
- ₹17,702.20/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.6.3 (Providing and fixing one piece construction white vitreous china squatting plate with an integral longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I. / PVC flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P. brass coupling complete, including painting of fittings and cutting and making good the walls and floors etc. wherever required : Range of three squatting plates with 10 litre P.V.C. automatic flushing cistern) is derived from 10 priced inputs for one no and works out to ₹17,702.20 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1915 | MAT | Vitreous china squatting plate urinal | each | 3 | 1,158.00 | 3,474.00 |
| 7361 | MAT | P.V.C. automatic flushing cistern 10 lts capacityP.V.C. automatic flushing cistern 10 litre capacity | each | 1 | 545.00 | 545.00 |
| 1542 | MAT | Flush pipe and spreaders G.I.for range of three squatting plates urinalFlush pipe and spreaders G.l. for range of three squatting plates urinal | each | 1 | 330.00 | 330.00 |
| 9999 | MAT | Red lead, white lead and gaskit | L.S. | 17.55 | 2.27 | 39.84 |
| 9999 | MAT | Cement, sand and grit etc. | L.S. | 80.73 | 2.27 | 183.26 |
| 9999 | MAT | Painting of fittings etc. | L.S. | 26 | 2.27 | 59.02 |
| 9977 | MAT | Carriage of materials | L.S. | 42.12 | 2.27 | 95.61 |
| 0116 | LAB | Fitter (grade 1) | day | 3 | 897.00 | 2,691.00 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 1.5 | 897.00 | 1,345.50 |
| 0114 | LAB | Beldar | day | 5 | 736.00 | 3,680.00 |
- TOTAL
- 12,443.23
- Add 1 % Water charges on “W”
- +124.43
- TOTAL
- 12,567.66
- Add GST on “X” (multiplying factor 0.2127)
- +2,673.14
- TOTAL
- 15,240.80
- Add 15% CPOH on “Y”
- +2,286.12
- TOTAL
- 17,526.92
- Add Cess @ 1% on “Z”
- +175.27
- Cost of each
- 17,702.19
- SAY
- ₹17,702.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1292
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1292. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.