CPWD Analysis of Rates · Sanitary Installations
Providing and fixing one piece construction white vitreous china squatting plate with an integral longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I. / PVC flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P. brass coupling complete, including painting of fittings and cutting and making good the walls and floors etc. wherever required
Range of three squatting plates with 10 litre P.V.C. automatic flushing cistern
- Item number
- 17.6.3
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 10
- Derived rate
- ₹17,702.20 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.6.3 — Providing and fixing one piece construction white vitreous china squatting plate with an integral longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I. / PVC flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P. brass coupling complete, including painting of fittings and cutting and making good the walls and floors etc. wherever required : Range of three squatting plates with 10 litre P.V.C. automatic flushing cistern — is derived from 10 priced inputs for one no and works out to ₹17,702.20 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1915 | Vitreous china squatting plate urinalMaterial | each | 3 | 1,158.00 | 3,474.00 |
| 7361 | P.V.C. automatic flushing cistern 10 lts capacityP.V.C. automatic flushing cistern 10 litre capacityMaterial | each | 1 | 545.00 | 545.00 |
| 1542 | Flush pipe and spreaders G.I.for range of three squatting plates urinalFlush pipe and spreaders G.l. for range of three squatting plates urinalMaterial | each | 1 | 330.00 | 330.00 |
| 9999 | Red lead, white lead and gaskitMaterial | L.S. | 17.55 | 2.27 | 39.84 |
| 9999 | Cement, sand and grit etc.Material | L.S. | 80.73 | 2.27 | 183.26 |
| 9999 | Painting of fittings etc.Material | L.S. | 26 | 2.27 | 59.02 |
| 9977 | Carriage of materialsMaterial | L.S. | 42.12 | 2.27 | 95.61 |
| 0116 | Fitter (grade 1)Labour | day | 3 | 897.00 | 2,691.00 |
| 0123 | Mason 1st classMason 1st classLabour | day | 1.5 | 897.00 | 1,345.50 |
| 0114 | BeldarLabour | day | 5 | 736.00 | 3,680.00 |
- TOTAL
- 12,443.23
- Add 1 % Water charges on “W”
- 124.43
- TOTAL
- 12,567.66
- Add GST on “X” (multiplying factor 0.2127)
- 2,673.14
- TOTAL
- 15,240.80
- Add 15% CPOH on “Y”
- 2,286.12
- TOTAL
- 17,526.92
- Add Cess @ 1% on “Z”
- 175.27
- Cost of each
- 17,702.19
- Say
- 17,702.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1292. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.