CPWD Analysis of Rates · Sanitary Installations

Providing and fixing one piece construction white vitreous china squatting plate with an integral longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I. / PVC flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P. brass coupling complete, including painting of fittings and cutting and making good the walls and floors etc. wherever required

Single squatting plate with 5 litre P.V.C. automatic flushing cistern

Item number
17.6.1
Analysis basis
Details of cost for one no.
Priced inputs
10
Derived rate
9,256.45 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.6.1 Providing and fixing one piece construction white vitreous china squatting plate with an integral longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I. / PVC flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P. brass coupling complete, including painting of fittings and cutting and making good the walls and floors etc. wherever required : Single squatting plate with 5 litre P.V.C. automatic flushing cistern — is derived from 10 priced inputs for one no and works out to ₹9,256.45 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1915Vitreous china squatting plate urinalMaterialeach11,158.001,158.00
7359P.V.C. automatic flushing cistern 5 lts capacityP.V.C. automatic flushing cistern 5 litre capacityMaterialeach1477.00477.00
1540Flush pipe and spreaders G.I.for single set of one squatting plate urinalFlush pipe and spreaders G.l. for single set of one squatting plate urinalMaterialeach1200.00200.00
9999Red lead, white lead and gaskitMaterialL.S.17.552.2739.84
9999Cement, sand and grit etc.MaterialL.S.26.912.2761.09
9999Painting of fittings etc.MaterialL.S.262.2759.02
9977Carriage of materialsMaterialL.S.26.912.2761.09
0116Fitter (grade 1)Labourday1.75897.001,569.75
0123Mason 1st classMason 1st classLabourday0.75897.00672.75
0114BeldarLabourday3736.002,208.00
TOTAL
6,506.54
Add 1 % Water charges on “W”
65.07
TOTAL
6,571.61
Add GST on “X” (multiplying factor 0.2127)
1,397.78
TOTAL
7,969.39
Add 15% CPOH on “Y”
1,195.41
TOTAL
9,164.80
Add Cess @ 1% on “Z”
91.65
Cost of each
9,256.45
Say
9,256.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1290. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.