Skip to main content
R/DAR 2023

Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required

Range of three urinal basins with 10litre white P.V.C. automatic flushing cistern
Item number
17.4.3
Analysis basis
one no
Priced inputs
11
Derived rate
₹13,417.30/ ONE NO
D-01/RATE ANALYSISITEM 17.4.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.4.3 (Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required : Range of three urinal basins with 10litre white P.V.C. automatic flushing cistern) is derived from 11 priced inputs for one no and works out to ₹13,417.30 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.4.3DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1913MATVitreous china lipped front urinaleach3517.001,551.00
7361MATP.V.C. automatic flushing cistern 10 lts capacityP.V.C. automatic flushing cistern 10 litre capacityeach1545.00545.00
7377MATG.I. flush pipe and C.P. brass spreader including C.P. connecting pipe Range of three lipped urinalseach11,130.001,130.00
9999MATRed lead, white lead and gaskitL.S.33.672.2776.43
9999MATPlugs ,screws etc.L.S.33.672.2776.43
9999MATCement, sand and grit etc.L.S.33.672.2776.43
9999MATPainting of fittings etc.L.S.392.2788.53
9977MATCarriage of materialsL.S.40.32.2791.48
0116LABFitter (grade 1)day2897.001,794.00
0123LABMason 1st classMason 1st classday2897.001,794.00
0114LABBeldarday3736.002,208.00
BUILD-UP TO RATE
TOTAL
9,431.30
Add 1 % Water charges on “W”
+94.31
TOTAL
9,525.61
Add GST on “X” (multiplying factor 0.2127)
+2,026.10
TOTAL
11,551.71
Add 15% CPOH on “Y”
+1,732.76
TOTAL
13,284.47
Add Cess @ 1% on “Z”
+132.84
Cost of each
13,417.31
SAY
₹13,417.30
D-02/SOURCEPRINTED PAGE 1286
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1286

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1286. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.