Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required

Range of two urinal basins with 5 litre white P.V.C. automatic flushing cistern
Item number
17.4.2
Analysis basis
one no
Priced inputs
11
Derived rate
₹9,612.40/ ONE NO
D-01/RATE ANALYSISITEM 17.4.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.4.2 (Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required : Range of two urinal basins with 5 litre white P.V.C. automatic flushing cistern) is derived from 11 priced inputs for one no and works out to ₹9,612.40 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.4.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1913MATVitreous china lipped front urinaleach2517.001,034.00
7359MATP.V.C. automatic flushing cistern 5 lts capacityP.V.C. automatic flushing cistern 5 litre capacityeach1477.00477.00
7376MATG.I. flush pipe and C.P. brass spreader including C.P. connecting pipe Range of two lipped urinalseach1795.00795.00
9999MATRed lead, white lead and gaskitL.S.20.282.2746.04
9999MATPlugs ,screws etc.L.S.20.282.2746.04
9999MATCement, sand and grit etc.L.S.20.282.2746.04
9999MATPainting of fittings etc.L.S.392.2788.53
9977MATCarriage of materialsL.S.26.912.2761.09
0116LABFitter (grade 1)day1.5897.001,345.50
0123LABMason 1st classMason 1st classday1.5897.001,345.50
0114LABBeldarday2736.001,472.00
BUILD-UP TO RATE
TOTAL
6,756.74
Add 1 % Water charges on “W”
+67.57
TOTAL
6,824.31
Add GST on “X” (multiplying factor 0.2127)
+1,451.53
TOTAL
8,275.84
Add 15% CPOH on “Y”
+1,241.38
TOTAL
9,517.22
Add Cess @ 1% on “Z”
+95.17
Cost of each
9,612.39
SAY
₹9,612.40
D-02/SOURCEPRINTED PAGE 1285
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1285

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1285. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS