CPWD Analysis of Rates · Sanitary Installations

Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required

One urinal basin with 5 litre white P.V.C. automatic flushing cistern

Item number
17.4.1
Analysis basis
Details of cost for one no.
Priced inputs
11
Derived rate
6,258.75 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.4.1 Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required : One urinal basin with 5 litre white P.V.C. automatic flushing cistern — is derived from 11 priced inputs for one no and works out to ₹6,258.75 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1913Vitreous china lipped front urinalMaterialeach1517.00517.00
7359P.V.C. automatic flushing cistern 5 lts capacityP.V.C. automatic flushing cistern 5 litre capacityMaterialeach1477.00477.00
7375G.I. flush pipe and C.P. brass spreader including C.P. connecting pipe Single lipped urinalMaterialeach1481.00481.00
9999Red lead, white lead and gaskitMaterialL.S.13.522.2730.69
9999Plugs ,screws etc.MaterialL.S.13.522.2730.69
9999Cement, sand and grit etc.MaterialL.S.13.522.2730.69
9999Painting of fittings etc.MaterialL.S.392.2788.53
9977Carriage of materialsMaterialL.S.26.912.2761.09
0116Fitter (grade 1)Labourday0.88897.00789.36
0123Mason 1st classMason 1st classLabourday0.88897.00789.36
0114BeldarLabourday1.5736.001,104.00
TOTAL
4,399.41
Add 1 % Water charges on “W”
43.99
TOTAL
4,443.40
Add GST on “X” (multiplying factor 0.2127)
945.11
TOTAL
5,388.51
Add 15% CPOH on “Y”
808.28
TOTAL
6,196.79
Add Cess @ 1% on “Z”
61.97
Cost of each
6,258.76
Say
6,258.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1285. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.