CPWD Analysis of Rates · Sanitary Installations

Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required

Range of four urinal basins with 10 litre white P.V.C. automatic flushing cistern

Item number
17.4.4
Analysis basis
Details of cost for one no.
Priced inputs
11
Derived rate
18,579.95 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.4.4 Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm and 340x410x265 mm sizes respectively with automatic flushing cistern with standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including painting of fittings and brackets, cutting and making good the walls and floors wherever required : Range of four urinal basins with 10 litre white P.V.C. automatic flushing cistern — is derived from 11 priced inputs for one no and works out to ₹18,579.95 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1913Vitreous china lipped front urinalMaterialeach4517.002,068.00
7361P.V.C. automatic flushing cistern 10 lts capacityP.V.C. automatic flushing cistern 10 litre capacityMaterialeach1545.00545.00
7378G.I. flush pipe and C.P. brass spreader including C.P. connecting pipe Range of four lipped urinalsMaterialeach11,544.001,544.00
9999Red lead, white lead and gaskitMaterialL.S.53.822.27122.17
9999Plugs ,screws etc.MaterialL.S.53.822.27122.17
9999Cement, sand and grit etc.MaterialL.S.53.822.27122.17
9999Painting of fittings etc.MaterialL.S.392.2788.53
9977Carriage of materialsMaterialL.S.53.822.27122.17
0116Fitter (grade 1)Labourday3897.002,691.00
0123Mason 1st classMason 1st classLabourday3897.002,691.00
0114BeldarLabourday4736.002,944.00
TOTAL
13,060.21
Add 1 % Water charges on “W”
130.60
TOTAL
13,190.81
Add GST on “X” (multiplying factor 0.2127)
2,805.69
TOTAL
15,996.50
Add 15% CPOH on “Y”
2,399.48
TOTAL
18,395.98
Add Cess @ 1% on “Z”
183.96
Cost of each
18,579.94
Say
18,579.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1287. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.