Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes

75 mm dia pipe

Item number
17.36.1
Analysis basis
Details of cost for 4 joints
Priced inputs
3
Derived rate
168.20 / joint

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.36.1 Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes : 75 mm dia pipe — is derived from 3 priced inputs for 4 joints and works out to ₹168.20 per joint after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
9999Cement mortar, spun yarn etc.MaterialL.S.6.892.2715.64
0116Fitter (grade 1)Labourday0.28897.00251.16
0114BeldarLabourday0.28736.00206.08
TOTAL
472.88
Add 1 % Water charges on “W”
4.73
TOTAL
477.61
Add GST on “X” (multiplying factor 0.2127)
101.59
TOTAL
579.20
Add 15% CPOH on “Y”
86.88
TOTAL
666.08
Add Cess @ 1% on “Z”
6.66
Cost of 4 joints
672.74
Cost of 1 joint
168.19
Say
168.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1332. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.