CPWD Analysis of Rates · Sanitary Installations
Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes
75 mm dia pipe
- Item number
- 17.36.1
- Analysis basis
- Details of cost for 4 joints
- Priced inputs
- 3
- Derived rate
- ₹168.20 / joint
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.36.1 — Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes : 75 mm dia pipe — is derived from 3 priced inputs for 4 joints and works out to ₹168.20 per joint after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 9999 | Cement mortar, spun yarn etc.Material | L.S. | 6.89 | 2.27 | 15.64 |
| 0116 | Fitter (grade 1)Labour | day | 0.28 | 897.00 | 251.16 |
| 0114 | BeldarLabour | day | 0.28 | 736.00 | 206.08 |
- TOTAL
- 472.88
- Add 1 % Water charges on “W”
- 4.73
- TOTAL
- 477.61
- Add GST on “X” (multiplying factor 0.2127)
- 101.59
- TOTAL
- 579.20
- Add 15% CPOH on “Y”
- 86.88
- TOTAL
- 666.08
- Add Cess @ 1% on “Z”
- 6.66
- Cost of 4 joints
- 672.74
- Cost of 1 joint
- 168.19
- Say
- 168.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1332. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.