Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes
- Item number
- 17.36.1
- Analysis basis
- 4 joints
- Priced inputs
- 3
- Derived rate
- ₹168.20/ JOINT
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.36.1 (Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes : 75 mm dia pipe) is derived from 3 priced inputs for 4 joints and works out to ₹168.20 per joint after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 9999 | MAT | Cement mortar, spun yarn etc. | L.S. | 6.89 | 2.27 | 15.64 |
| 0116 | LAB | Fitter (grade 1) | day | 0.28 | 897.00 | 251.16 |
| 0114 | LAB | Beldar | day | 0.28 | 736.00 | 206.08 |
- TOTAL
- 472.88
- Add 1 % Water charges on “W”
- +4.73
- TOTAL
- 477.61
- Add GST on “X” (multiplying factor 0.2127)
- +101.59
- TOTAL
- 579.20
- Add 15% CPOH on “Y”
- +86.88
- TOTAL
- 666.08
- Add Cess @ 1% on “Z”
- +6.66
- Cost of 4 joints
- 672.74
- Cost of 1 joint
- 168.19
- SAY
- ₹168.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1332
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1332. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.