Providing and fixing soil, waste and vent pipes : 75 mm diameter

Hubless centrifugally cast (spun) iron pipes epoxy coated inside & outside IS:15905
Item number
17.35.2.3
Analysis basis
18.00 m
Priced inputs
6
Derived rate
₹964.25/ METRE
D-01/RATE ANALYSISITEM 17.35.2.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.35.2.3 (Providing and fixing soil, waste and vent pipes : 75 mm diameter : Hubless centrifugally cast (spun) iron pipes epoxy coated inside & outside IS:15905) is derived from 6 priced inputs for 18.00 m and works out to ₹964.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • i/c (3% wastage)
ANALYSIS OF RATES · ITEM 17.35.2.3DETAIL OF COST FOR 18.00 M (6 X 3.00 M)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7622MATHubless centrifugally cast (spun) iron pipes as per IS 15905 - 75 mm dia (3000 mm length pipe)metre18.54591.0010,957.14
9999MATScaffoldingL.S.80.732.27183.26
9977MATCarriage of materialsL.S.40.382.2791.66
0116LABFitter (grade 1)day0.35897.00313.95
0100LABBandhaniday0.17816.00138.72
0114LABBeldarday0.7736.00515.20
BUILD-UP TO RATE
TOTAL
12,199.93
Add 1 % Water charges on “W”
+122.00
TOTAL
12,321.93
Add GST on “X” (multiplying factor 0.2127)
+2,620.87
TOTAL
14,942.80
Add 15% CPOH on “Y”
+2,241.42
TOTAL
17,184.22
Add Cess @ 1% on “Z”
+171.84
Cost of 18.00 metre
17,356.06
Cost of 1 metre
964.23
SAY
₹964.25
D-02/SOURCEPRINTED PAGE 1331
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1331

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1331. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.