Providing and fixing soil, waste and vent pipes : 75 mm diameter

Centrifugally cast (spun) iron socketed pipe as per IS: 3989
Item number
17.35.2.2
Analysis basis
16.92 m
Priced inputs
6
Derived rate
₹1,186.00/ M
D-01/RATE ANALYSISITEM 17.35.2.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.35.2.2 (Providing and fixing soil, waste and vent pipes : 75 mm diameter : Centrifugally cast (spun) iron socketed pipe as per IS: 3989) is derived from 6 priced inputs for 16.92 m and works out to ₹1,186.00 per m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (1.75mx10)-(9x0.065m) = 16.915 m. say
  • 16.92 m
  • including 5% allowance for wastage
ANALYSIS OF RATES · ITEM 17.35.2.2DETAILS OF COST FOR 16.92 M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3621MATC.C.I.(spun) socketed soil, waste and vent pipe 1.80 metres long:75mm diaC.C.I. (spun) socketed soil, waste and vent pipe 1.80 metres long:75 mm diaeach10.51,225.0012,862.50
9999MATScaffoldingL.S.80.732.27183.26
9977MATCarriage of materialsL.S.40.382.2791.66
0116LABFitter (grade 1)day0.35897.00313.95
0100LABBandhaniday0.17816.00138.72
0114LABBeldarday0.7736.00515.20
BUILD-UP TO RATE
TOTAL
14,105.29
Add 1 % Water charges on “W”
+141.05
TOTAL
14,246.34
Add GST on “X” (multiplying factor 0.2127)
+3,030.20
TOTAL
17,276.54
Add 15% CPOH on “Y”
+2,591.48
TOTAL
19,868.02
Add Cess @ 1% on “Z”
+198.68
Cost for 16.92 m pipe
20,066.70
Cost per metre
1,185.98
SAY
₹1,186.00
D-02/SOURCEPRINTED PAGE 1331
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1331

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1331. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.