CPWD Analysis of Rates · Sanitary Installations

Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes

100 mm dia pipe

Item number
17.36.2
Analysis basis
Details of cost for 4 joints
Priced inputs
3
Derived rate
198.15 / joint

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.36.2 Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes : 100 mm dia pipe — is derived from 3 priced inputs for 4 joints and works out to ₹198.15 per joint after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
9999Cement mortar, spun yarn etc.MaterialL.S.8.062.2718.30
0116Fitter (grade 1)Labourday0.33897.00296.01
0114BeldarLabourday0.33736.00242.88
TOTAL
557.19
Add 1 % Water charges on “W”
5.57
TOTAL
562.76
Add GST on “X” (multiplying factor 0.2127)
119.70
TOTAL
682.46
Add 15% CPOH on “Y”
102.37
TOTAL
784.83
Add Cess @ 1% on “Z”
7.85
Cost of 4 joints
792.68
Cost of 1 joint
198.17
Say
198.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1332. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.