Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes
- Item number
- 17.36.2
- Analysis basis
- 4 joints
- Priced inputs
- 3
- Derived rate
- ₹198.15/ JOINT
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.36.2 (Providing and filling the joints with spun yarn, cement slurry and cement mortar 1:2 (1 cement : 2 fine sand) in S.C.I./ C.I. Pipes : 100 mm dia pipe) is derived from 3 priced inputs for 4 joints and works out to ₹198.15 per joint after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 9999 | MAT | Cement mortar, spun yarn etc. | L.S. | 8.06 | 2.27 | 18.30 |
| 0116 | LAB | Fitter (grade 1) | day | 0.33 | 897.00 | 296.01 |
| 0114 | LAB | Beldar | day | 0.33 | 736.00 | 242.88 |
- TOTAL
- 557.19
- Add 1 % Water charges on “W”
- +5.57
- TOTAL
- 562.76
- Add GST on “X” (multiplying factor 0.2127)
- +119.70
- TOTAL
- 682.46
- Add 15% CPOH on “Y”
- +102.37
- TOTAL
- 784.83
- Add Cess @ 1% on “Z”
- +7.85
- Cost of 4 joints
- 792.68
- Cost of 1 joint
- 198.17
- SAY
- ₹198.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1332
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1332. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.