CPWD Analysis of Rates · Sanitary Installations
Providing and fixing soil, waste and vent pipes : 100 mm dia
Hubless centrifugally cast (spun) iron pipes epoxy coated inside & outside IS:15905
- Item number
- 17.35.1.3
- Analysis basis
- Detail of cost for 18.00 m (6 x 3.00 m)
- Priced inputs
- 6
- Derived rate
- ₹1,169.30 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.35.1.3 — Providing and fixing soil, waste and vent pipes : 100 mm dia Hubless centrifugally cast (spun) iron pipes epoxy coated inside & outside IS:15905 — is derived from 6 priced inputs for 18.00 m and works out to ₹1,169.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- i/c (3% wastage)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7621 | Hubless centrifugally cast (spun) iron pipes as per IS 15905 - 100 mm dia (3000 mm length pipe)Material | metre | 18.54 | 719.00 | 13,330.26 |
| 9999 | ScaffoldingMaterial | L.S. | 80.73 | 2.27 | 183.26 |
| 9977 | Carriage of materialsMaterial | L.S. | 53.82 | 2.27 | 122.17 |
| 0116 | Fitter (grade 1)Labour | day | 0.42 | 897.00 | 376.74 |
| 0100 | BandhaniLabour | day | 0.21 | 816.00 | 171.36 |
| 0114 | BeldarLabour | day | 0.83 | 736.00 | 610.88 |
- TOTAL
- 14,794.67
- Add 1 % Water charges on “W”
- 147.95
- TOTAL
- 14,942.62
- Add GST on “X” (multiplying factor 0.2127)
- 3,178.30
- TOTAL
- 18,120.92
- Add 15% CPOH on “Y”
- 2,718.14
- TOTAL
- 20,839.06
- Add Cess @ 1% on “Z”
- 208.39
- Cost of 18.00 metre
- 21,047.45
- Cost of 1 metre
- 1,169.30
- Say
- 1,169.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1329. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works