Providing and fixing soil, waste and vent pipes : 100 mm dia
- Item number
- 17.35.1.3
- Analysis basis
- 18.00 m
- Priced inputs
- 6
- Derived rate
- ₹1,169.30/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.35.1.3 (Providing and fixing soil, waste and vent pipes : 100 mm dia Hubless centrifugally cast (spun) iron pipes epoxy coated inside & outside IS:15905) is derived from 6 priced inputs for 18.00 m and works out to ₹1,169.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- i/c (3% wastage)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7621 | MAT | Hubless centrifugally cast (spun) iron pipes as per IS 15905 - 100 mm dia (3000 mm length pipe) | metre | 18.54 | 719.00 | 13,330.26 |
| 9999 | MAT | Scaffolding | L.S. | 80.73 | 2.27 | 183.26 |
| 9977 | MAT | Carriage of materials | L.S. | 53.82 | 2.27 | 122.17 |
| 0116 | LAB | Fitter (grade 1) | day | 0.42 | 897.00 | 376.74 |
| 0100 | LAB | Bandhani | day | 0.21 | 816.00 | 171.36 |
| 0114 | LAB | Beldar | day | 0.83 | 736.00 | 610.88 |
- TOTAL
- 14,794.67
- Add 1 % Water charges on “W”
- +147.95
- TOTAL
- 14,942.62
- Add GST on “X” (multiplying factor 0.2127)
- +3,178.30
- TOTAL
- 18,120.92
- Add 15% CPOH on “Y”
- +2,718.14
- TOTAL
- 20,839.06
- Add Cess @ 1% on “Z”
- +208.39
- Cost of 18.00 metre
- 21,047.45
- Cost of 1 metre
- 1,169.30
- SAY
- ₹1,169.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1329
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1329. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.