Skip to main content
R/DAR 2023

Providing and fixing soil, waste and vent pipes : 100 mm dia

Hubless centrifugally cast (spun) iron pipes epoxy coated inside & outside IS:15905
Item number
17.35.1.3
Analysis basis
18.00 m
Priced inputs
6
Derived rate
₹1,169.30/ METRE
D-01/RATE ANALYSISITEM 17.35.1.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.35.1.3 (Providing and fixing soil, waste and vent pipes : 100 mm dia Hubless centrifugally cast (spun) iron pipes epoxy coated inside & outside IS:15905) is derived from 6 priced inputs for 18.00 m and works out to ₹1,169.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • i/c (3% wastage)
ANALYSIS OF RATES · ITEM 17.35.1.3DETAIL OF COST FOR 18.00 M (6 X 3.00 M)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7621MATHubless centrifugally cast (spun) iron pipes as per IS 15905 - 100 mm dia (3000 mm length pipe)metre18.54719.0013,330.26
9999MATScaffoldingL.S.80.732.27183.26
9977MATCarriage of materialsL.S.53.822.27122.17
0116LABFitter (grade 1)day0.42897.00376.74
0100LABBandhaniday0.21816.00171.36
0114LABBeldarday0.83736.00610.88
BUILD-UP TO RATE
TOTAL
14,794.67
Add 1 % Water charges on “W”
+147.95
TOTAL
14,942.62
Add GST on “X” (multiplying factor 0.2127)
+3,178.30
TOTAL
18,120.92
Add 15% CPOH on “Y”
+2,718.14
TOTAL
20,839.06
Add Cess @ 1% on “Z”
+208.39
Cost of 18.00 metre
21,047.45
Cost of 1 metre
1,169.30
SAY
₹1,169.30
D-02/SOURCEPRINTED PAGE 1329
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1329

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1329. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.