Providing and fixing soil, waste and vent pipes : 100 mm dia
- Item number
- 17.35.1.1
- Analysis basis
- 17.37 m
- Priced inputs
- 6
- Derived rate
- ₹1,151.90/ M
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.35.1.1 (Providing and fixing soil, waste and vent pipes : 100 mm dia Sand cast iron S&S pipe as per IS: 1729) is derived from 6 priced inputs for 17.37 m and works out to ₹1,151.90 per m after water charges, GST, CPOH and cess. The full build-up is below.
- (1.8mx10)-(9x0.07m) = 17.37 m
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1617 | MAT | S.C.I. soil, waste and vent single socketed pipe 1.80 metres long: 100mm diaS.C.I. soil, waste and vent single socketed pipe 1.80 metres long:100 mm dia | each | 10.5 | 1,200.00 | 12,600.00 |
| 9999 | MAT | Scaffolding | L.S. | 80.73 | 2.27 | 183.26 |
| 9977 | MAT | Carriage of materials | L.S. | 53.82 | 2.27 | 122.17 |
| 0116 | LAB | Fitter (grade 1) | day | 0.42 | 897.00 | 376.74 |
| 0100 | LAB | Bandhani | day | 0.21 | 816.00 | 171.36 |
| 0114 | LAB | Beldar | day | 0.83 | 736.00 | 610.88 |
- TOTAL
- 14,064.41
- Add 1 % Water charges on “W”
- +140.64
- TOTAL
- 14,205.05
- Add GST on “X” (multiplying factor 0.2127)
- +3,021.41
- TOTAL
- 17,226.46
- Add 15% CPOH on “Y”
- +2,583.97
- TOTAL
- 19,810.43
- Add Cess @ 1% on “Z”
- +198.10
- Cost for 17.37 m pipe
- 20,008.53
- Cost per metre
- 1,151.90
- SAY
- ₹1,151.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1328
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1328. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.