Skip to main content
R/DAR 2023

Providing and fixing soil, waste and vent pipes : 100 mm dia

Sand cast iron S&S pipe as per IS: 1729
Item number
17.35.1.1
Analysis basis
17.37 m
Priced inputs
6
Derived rate
₹1,151.90/ M
D-01/RATE ANALYSISITEM 17.35.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.35.1.1 (Providing and fixing soil, waste and vent pipes : 100 mm dia Sand cast iron S&S pipe as per IS: 1729) is derived from 6 priced inputs for 17.37 m and works out to ₹1,151.90 per m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (1.8mx10)-(9x0.07m) = 17.37 m
ANALYSIS OF RATES · ITEM 17.35.1.1DETAILS OF COST FOR 17.37 M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1617MATS.C.I. soil, waste and vent single socketed pipe 1.80 metres long: 100mm diaS.C.I. soil, waste and vent single socketed pipe 1.80 metres long:100 mm diaeach10.51,200.0012,600.00
9999MATScaffoldingL.S.80.732.27183.26
9977MATCarriage of materialsL.S.53.822.27122.17
0116LABFitter (grade 1)day0.42897.00376.74
0100LABBandhaniday0.21816.00171.36
0114LABBeldarday0.83736.00610.88
BUILD-UP TO RATE
TOTAL
14,064.41
Add 1 % Water charges on “W”
+140.64
TOTAL
14,205.05
Add GST on “X” (multiplying factor 0.2127)
+3,021.41
TOTAL
17,226.46
Add 15% CPOH on “Y”
+2,583.97
TOTAL
19,810.43
Add Cess @ 1% on “Z”
+198.10
Cost for 17.37 m pipe
20,008.53
Cost per metre
1,151.90
SAY
₹1,151.90
D-02/SOURCEPRINTED PAGE 1328
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1328

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1328. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.