Providing and fixing toilet paper holder
- Item number
- 17.34.2
- Analysis basis
- Details of cost of one no.
- Priced inputs
- 6
- Derived rate
- ₹546.35
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.34.2 (Providing and fixing toilet paper holder : Vitreous china) is derived from 6 priced inputs and works out to ₹546.35 after water charges, GST, CPOH and cess. The full build-up is below.
- Wooden cleats
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 3749 | MAT | Vitreous china toilet paper holder of standard size | each | 1 | 120.00 | 120.00 |
| SUB | Rate as per item no 8.23 of SH : Cladding workRate as per item 8.23 | each | 2 | 40.85 | 81.70 | |
| 0588 | MAT | Chromium plated Brass screws 25 mm | 100 Nos | 0.06 | 177.00 | 10.62 |
| 9977 | MAT | Carriage of materials | L.S. | 4.29 | 2.27 | 9.74 |
| 0112 | LAB | Carpenter 2nd class | day | 0.12 | 816.00 | 97.92 |
| 0114 | LAB | Beldar | day | 0.12 | 736.00 | 88.32 |
- TOTAL
- 408.30
- Add 1 % Water charges on “W-A”
- +3.27
- TOTAL
- 411.57
- Add GST on “X-A” (multiplying factor 0.2127)
- +70.16
- TOTAL
- 481.73
- Add 15% CPOH on “Y-A”
- +60.00
- TOTAL
- 541.73
- Add Cess @ 1% on “Z-A”
- +4.60
- Cost of each
- 546.33
- SAY
- ₹546.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1328
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1328. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.