Skip to main content
R/DAR 2023

Providing and fixing toilet paper holder

C.P. brass
Item number
17.34.1
Analysis basis
one no
Priced inputs
6
Derived rate
₹803.70/ ONE NO
D-01/RATE ANALYSISITEM 17.34.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.34.1 (Providing and fixing toilet paper holder : C.P. brass) is derived from 6 priced inputs for one no and works out to ₹803.70 per one no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Wooden cleats
ANALYSIS OF RATES · ITEM 17.34.1DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1889MATC.P.brass toilet paper holder of standard sizeC.P. brass toilet paper holder of standard sizeeach1308.00308.00
SUBRate as per item no 8.23 of SH : Cladding workRate as per item 8.23each240.8581.70
0588MATChromium plated Brass screws 25 mm100 Nos0.02177.003.54
9977MATCarriage of materialsL.S.4.292.279.74
0112LABCarpenter 2nd classday0.12816.0097.92
0114LABBeldarday0.12736.0088.32
BUILD-UP TO RATE
TOTAL
589.22
Add 1 % Water charges on “W-A”
+5.08
TOTAL
594.30
Add GST on “X-A” (multiplying factor 0.2127)
+109.03
TOTAL
703.33
Add 15% CPOH on “Y-A”
+93.24
TOTAL
796.57
Add Cess @ 1% on “Z-A”
+7.15
Cost of each
803.72
SAY
₹803.70
D-02/SOURCEPRINTED PAGE 1327
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1327

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1327. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.