CPWD Analysis of Rates · Sanitary Installations
Providing and fixing 600x120x5 mm glass shelf with edges round off, supported on anodised aluminium angle frame with C.P. brass brackets and guard rail complete fixed with 40 mm long screws, rawl plugs etc., complete
- Item number
- 17.33
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 6
- Derived rate
- ₹1,083.50 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.33 — Providing and fixing 600x120x5 mm glass shelf with edges round off, supported on anodised aluminium angle frame with C.P. brass brackets and guard rail complete fixed with 40 mm long screws, rawl plugs etc., complete — is derived from 6 priced inputs for one no and works out to ₹1,083.50 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 3228 | 600x120 mm glass shelf with anodised aluminium angle frame, C.P. brass brackets and guard rail of standard sizeMaterial | each | 1 | 306.00 | 306.00 |
| 7048 | Rawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)Material | each | 2 | 24.00 | 48.00 |
| 0586 | Chromium plated Brass screws 40 mmMaterial | 100 Nos | 0.04 | 254.00 | 10.16 |
| 9977 | Carriage of materialsMaterial | L.S. | 4.16 | 2.27 | 9.44 |
| 0112 | Carpenter 2nd classLabour | day | 0.25 | 816.00 | 204.00 |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
- TOTAL
- 761.60
- Add 1 % Water charges on “W”
- 7.62
- TOTAL
- 769.22
- Add GST on “X” (multiplying factor 0.2127)
- 163.61
- TOTAL
- 932.83
- Add 15% CPOH on “Y”
- 139.92
- TOTAL
- 1,072.75
- Add Cess @ 1% on “Z”
- 10.73
- Cost of each
- 1,083.48
- Say
- 1,083.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1327. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.