Skip to main content
R/DAR 2023

Providing and fixing 8 mm dia C.P. / S.S. Jet with flexible tube upto 1 metre long with S.S. triangular plate to Eureopean type W.C. of quality and make as approved by Engineer - in - charge

Item number
17.16A
Analysis basis
1 No
Priced inputs
2
Derived rate
₹349.15/ NO
D-01/RATE ANALYSISITEM 17.16A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.16A (Providing and fixing 8 mm dia C.P. / S.S. Jet with flexible tube upto 1 metre long with S.S. triangular plate to Eureopean type W.C. of quality and make as approved by Engineer - in - charge) is derived from 2 priced inputs for 1 No and works out to ₹349.15 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.16ADETAILS OF COST FOR 1 NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1313MAT8 mm dia C.P. Brass/ S.S. Jet with flexible tube upto 1 metre long with S.S. tringular plate for Eureopean type W.C.(Hindware/ Kingston/Prima/Parko/Marc)8 mm dia C.P. Brass/ S.S. Jet with flexible tube upto 1 metre long with S.S. tringular plate for Eureopean type W.C.each1220.00220.00
9999MATCarriage of material and fixing chargesL.S.11.22.2725.42
BUILD-UP TO RATE
TOTAL
245.42
Add 1 % Water charges on “W”
+2.45
TOTAL
247.87
Add GST on “X” (multiplying factor 0.2127)
+52.72
TOTAL
300.59
Add 15% CPOH on “Y”
+45.09
TOTAL
345.68
Add Cess @ 1% on “Z”
+3.46
Cost of each
349.14
SAY
₹349.15
D-02/SOURCEPRINTED PAGE 1310
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1310

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1310. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.