Skip to main content
R/DAR 2023

Extra for using coloured pedestal type W.C pan (European type) with low level cistern of same colour instead of white vitreous china W.C pan and cistern

Item number
17.16
Analysis basis
one no
Priced inputs
4
Derived rate
₹170.70/ ONE NO
D-01/RATE ANALYSISITEM 17.16

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.16 (Extra for using coloured pedestal type W.C pan (European type) with low level cistern of same colour instead of white vitreous china W.C pan and cistern) is derived from 4 priced inputs for one no and works out to ₹170.70 per one no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Deduct
  • Deduct
ANALYSIS OF RATES · ITEM 17.16DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7105MATColoured Pedestal type W.C. pan 580x440 mm (European type)each1900.00900.00
1955MATVitreous china pedestal type water closeteach-11,080.00-1,080.00
7106MATColoured Vitreous china 10 lit. low level cisterneach11,000.001,000.00
7005MATVitreous china 10 litres low level cistern without fittingseach-1700.00-700.00
BUILD-UP TO RATE
TOTAL
120.00
Add 1 % Water charges on “W”
+1.20
TOTAL
121.20
Add GST on “X” (multiplying factor 0.2127)
+25.78
TOTAL
146.98
Add 15% CPOH on “Y”
+22.05
TOTAL
169.03
Add Cess @ 1% on “Z”
+1.69
Cost of each
170.72
SAY
₹170.70
D-02/SOURCEPRINTED PAGE 1310
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1310

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1310. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.