Skip to main content

CPWD Analysis of Rates · Sanitary Installations

Providing and fixing a pair of white vitreous china foot rests of standard pattern for squatting pan water closet

250x130x30 mm

Item number
17.17.1
Analysis basis
Details of cost for one pair
Priced inputs
3
Derived rate
244.85 / one pair

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.17.1 Providing and fixing a pair of white vitreous china foot rests of standard pattern for squatting pan water closet : 250x130x30 mm — is derived from 3 priced inputs for one pair and works out to ₹244.85 per one pair after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1363Vitreous china foot rests 250x130x30 mmMaterialpair1100.00100.00
9988Cement, sand including carriage of materialsMaterialL.S.8.062.2718.30
0123Mason 1st classMason 1st classLabourday0.06897.0053.82
TOTAL
172.12
Add 1 % Water charges on “W”
1.72
TOTAL
173.84
Add GST on “X” (multiplying factor 0.2127)
36.98
TOTAL
210.82
Add 15% CPOH on “Y”
31.62
TOTAL
242.44
Add Cess @ 1% on “Z”
2.42
Cost for 1 pair
244.86
Say
244.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1311. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.