Extra for straight cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated, semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter for chimney stacks, skylights etc

Item number
12.9
Analysis basis
3 metres
Priced inputs
2
Derived rate
₹92.95/ METRE OF PERIPHERY
D-01/RATE ANALYSISITEM 12.9

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.9 (Extra for straight cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated, semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter for chimney stacks, skylights etc) is derived from 2 priced inputs for 3 metres and works out to ₹92.95 per metre of periphery after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Area of cutting 0.9mx0.6m=0.54sqm.
  • Perimeter = 3 metres
ANALYSIS OF RATES · ITEM 12.9DETAILS OF COST FOR 3 METRES OF PERIPHERY
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0111LABCarpenter 1st classday0.12897.00107.64
0114LABBeldarday0.12736.0088.32
BUILD-UP TO RATE
TOTAL
195.96
Add 1 % Water charges on “W”
+1.96
TOTAL
197.92
Add GST on “X” (multiplying factor 0.2127)
+42.10
TOTAL
240.02
Add 15% CPOH on “Y”
+36.00
TOTAL
276.02
Add Cess @ 1% on “Z”
+2.76
Cost of 3.00 metres of periphery
278.78
Cost of 1.00 metre of periphery
92.93
SAY
₹92.95
D-02/SOURCEPRINTED PAGE 863
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
863

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 863. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.