Extra for circular cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated/ semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter

Item number
12.10
Analysis basis
4 holes
Priced inputs
2
Derived rate
₹256.70/ METRE OF PERIPHERY
D-01/RATE ANALYSISITEM 12.10

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.10 (Extra for circular cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated/ semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter) is derived from 2 priced inputs for 4 holes and works out to ₹256.70 per metre of periphery after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • diameter i.e. 9.05 metre periphery
ANALYSIS OF RATES · ITEM 12.10DETAILS OF COST FOR 4 HOLES OF 0.72 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0111LABCarpenter 1st classday1897.00897.00
0114LABBeldarday1736.00736.00
BUILD-UP TO RATE
TOTAL
1,633.00
Add 1 % Water charges on “W”
+16.33
TOTAL
1,649.33
Add GST on “X” (multiplying factor 0.2127)
+350.81
TOTAL
2,000.14
Add 15% CPOH on “Y”
+300.02
TOTAL
2,300.16
Add Cess @ 1% on “Z”
+23.00
Cost of 9.05 metres of periphery
2,323.16
Cost of 1.00 metre of periphery
256.70
SAY
₹256.70
D-02/SOURCEPRINTED PAGE 864
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
864

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 864. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.