Extra for circular cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated/ semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter

Item number
12.10
Analysis basis
Details of cost for 4 holes of 0.72 metre
Priced inputs
2
Derived rate
256.70 / metre of periphery

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.10 Extra for circular cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated/ semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter — is derived from 2 priced inputs for 4 holes and works out to ₹256.70 per metre of periphery after water charges, GST, CPOH and cess. The full build-up is below.

  • diameter i.e. 9.05 metre periphery
CodeInputUnitQuantityRate (INR)Amount (INR)
0111Carpenter 1st classLabourday1897.00897.00
0114BeldarLabourday1736.00736.00
TOTAL
1,633.00
Add 1 % Water charges on “W”
16.33
TOTAL
1,649.33
Add GST on “X” (multiplying factor 0.2127)
350.81
TOTAL
2,000.14
Add 15% CPOH on “Y”
300.02
TOTAL
2,300.16
Add Cess @ 1% on “Z”
23.00
Cost of 9.05 metres of periphery
2,323.16
Cost of 1.00 metre of periphery
256.70
Say
256.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 864. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.