Providing reinforced by organic fibres and/or inorganic synthetic fibres cement 6 mm thick corrugated sheets (as per IS: 14871) roofing up to any pitch and fixing with polymer coated J, or L hooks, bolts and nuts 8 mm dia. G.I. plain and bitumen washers or with self drilling fastener and EPDM washers etc. complete (excluding the cost of purlins, rafters and trusses), including cutting sheets to size and shape wherever required
- Item number
- 12.8
- Analysis basis
- 216.14 sqm
- Priced inputs
- 9
- Derived rate
- ₹536.40/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.8 (Providing reinforced by organic fibres and/or inorganic synthetic fibres cement 6 mm thick corrugated sheets (as per IS: 14871) roofing up to any pitch and fixing with polymer coated J, or L hooks, bolts and nuts 8 mm dia. G.I. plain and bitumen washers or with self drilling fastener and EPDM washers etc. complete (excluding the cost of purlins, rafters and trusses), including cutting sheets to size and shape wherever required) is derived from 9 priced inputs for 216.14 sqm and works out to ₹536.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- upto 60° pitch
- Upto 60 degree pitch
- Consider a shed of 20x10 metres. (External
- dimensions of plinth).
- Area of roof- 20.2x10.70m = 216.14 sqm.
- Sheets used = 2x20 nos.x3.00mx1.05m
- =126.00sqm+
- 2x20nos.x2.50mx1.05m=105.00sqm.
- Total = 231.00sqm. +
- Total = 237.93sqm.
- 2x20x0.42147 = 1.68588 +
- 2x20x0.35123= 1.4049
- Total = 3.0908+
- Total = 3.1835 Say 3.184 t
- Add 3% wastage = 6.93
- Add 3 % wastage = 0.092
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0223 | MAT | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated sheet 6mm thickFibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated sheet 6 mm thick | sqm | 237.93 | 245.00 | 58,292.85 |
| 1023 | MAT | Galvanised steel J or L hooks 8 mm dia | 10 Nos | 47.6 | 130.00 | 6,188.00 |
| 1208 | MAT | Bitumen washer | 100 Nos | 4.76 | 30.00 | 142.80 |
| 1209 | MAT | G.I. plain washer thick | 100 Nos | 4.76 | 35.00 | 166.60 |
| 9977 | MAT | Carriage of bolts and nuts, washers etc. | L.S. | 8.06 | 2.27 | 18.30 |
| 9999 | MAT | Sundries | L.S. | 39.52 | 2.27 | 89.71 |
| 0130 | LAB | Mistry | day | 2.34 | 897.00 | 2,098.98 |
| 0112 | LAB | Carpenter 2nd class | day | 9.34 | 816.00 | 7,621.44 |
| 0114 | LAB | Beldar | day | 9.34 | 736.00 | 6,874.24 |
- TOTAL
- 81,492.92
- Add 1 % Water charges on “W”
- +814.93
- TOTAL
- 82,307.85
- Add GST on “X” (multiplying factor 0.2127)
- +17,506.88
- TOTAL
- 99,814.73
- Add 15% CPOH on “Y”
- +14,972.21
- TOTAL
- 1,14,786.94
- Add Cess @ 1% on “Z”
- +1,147.87
- Cost of 216.14 sqm.
- 1,15,934.81
- Cost of 1.00 sqm.
- 536.39
- SAY
- ₹536.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 862
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 862. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.