Providing reinforced by organic fibres and/or inorganic synthetic fibres cement 6 mm thick corrugated sheets (as per IS: 14871) roofing up to any pitch and fixing with polymer coated J, or L hooks, bolts and nuts 8 mm dia. G.I. plain and bitumen washers or with self drilling fastener and EPDM washers etc. complete (excluding the cost of purlins, rafters and trusses), including cutting sheets to size and shape wherever required

Item number
12.8
Analysis basis
216.14 sqm
Priced inputs
9
Derived rate
₹536.40/ SQM
D-01/RATE ANALYSISITEM 12.8

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.8 (Providing reinforced by organic fibres and/or inorganic synthetic fibres cement 6 mm thick corrugated sheets (as per IS: 14871) roofing up to any pitch and fixing with polymer coated J, or L hooks, bolts and nuts 8 mm dia. G.I. plain and bitumen washers or with self drilling fastener and EPDM washers etc. complete (excluding the cost of purlins, rafters and trusses), including cutting sheets to size and shape wherever required) is derived from 9 priced inputs for 216.14 sqm and works out to ₹536.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • upto 60° pitch
  • Upto 60 degree pitch
  • Consider a shed of 20x10 metres. (External
  • dimensions of plinth).
  • Area of roof- 20.2x10.70m = 216.14 sqm.
  • Sheets used = 2x20 nos.x3.00mx1.05m
  • =126.00sqm+
  • 2x20nos.x2.50mx1.05m=105.00sqm.
  • Total = 231.00sqm. +
  • Total = 237.93sqm.
  • 2x20x0.42147 = 1.68588 +
  • 2x20x0.35123= 1.4049
  • Total = 3.0908+
  • Total = 3.1835 Say 3.184 t
  • Add 3% wastage = 6.93
  • Add 3 % wastage = 0.092
ANALYSIS OF RATES · ITEM 12.8DETAILS OF COST FOR 216.14 SQM AREA OF ROOF
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0223MATFibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated sheet 6mm thickFibre reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated sheet 6 mm thicksqm237.93245.0058,292.85
1023MATGalvanised steel J or L hooks 8 mm dia10 Nos47.6130.006,188.00
1208MATBitumen washer100 Nos4.7630.00142.80
1209MATG.I. plain washer thick100 Nos4.7635.00166.60
9977MATCarriage of bolts and nuts, washers etc.L.S.8.062.2718.30
9999MATSundriesL.S.39.522.2789.71
0130LABMistryday2.34897.002,098.98
0112LABCarpenter 2nd classday9.34816.007,621.44
0114LABBeldarday9.34736.006,874.24
BUILD-UP TO RATE
TOTAL
81,492.92
Add 1 % Water charges on “W”
+814.93
TOTAL
82,307.85
Add GST on “X” (multiplying factor 0.2127)
+17,506.88
TOTAL
99,814.73
Add 15% CPOH on “Y”
+14,972.21
TOTAL
1,14,786.94
Add Cess @ 1% on “Z”
+1,147.87
Cost of 216.14 sqm.
1,15,934.81
Cost of 1.00 sqm.
536.39
SAY
₹536.40
D-02/SOURCEPRINTED PAGE 862
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
862

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 862. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.