Skip to main content

CPWD Analysis of Rates · Roofing

Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete

Precoated/mill finish aluminium Crimp curve

Item number
12.66.5
Analysis basis
Details of cost for 21.412 sqm
Priced inputs
8
Derived rate
914.70 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.66.5 Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium Crimp curve — is derived from 8 priced inputs for 21.412 sqm and works out to ₹914.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • crimp curve 20.2 metres long complete
  • length and 1.06 metre wide
  • Area 20.20 x 1.06 = 21.412 sqm + Add wastage @ 5% = 1.071 sqm. Total = 22.483 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
3072Precoated/Mill finish Aluminium crimp curveMaterialsqm22.48554.0012,455.58
3074Stainless steel self tapping screw of 6x50mm with SS hex cap and 3mm thick EPDM sealStainless steel self tapping screw of 6x50 mm with SS hex cap and 3 mm thick EPDM sealMaterial100 Nos0.4511.00204.40
9977Carriage of screws, washers and curvesMaterialL.S.9.882.2722.43
9999SundriesMaterialL.S.6.242.2714.16
LABOUROtherNaNNaN0.00
0130MistryLabourday0.1897.0089.70
0112Carpenter 2nd classLabourday0.3816.00244.80
0114BeldarLabourday1736.00736.00
Total
13,767.07
Add 1 % Water charges on “W”
137.67
TOTAL
13,904.74
Add GST on “X” (multiplying factor 0.2127)
2,957.54
TOTAL
16,862.28
Add 15% CPOH on “Y”
2,529.34
TOTAL
19,391.62
Add Cess @ 1% on “Z”
193.92
Cost of 21.412 metre
19,585.54
Cost of 1 metre
914.70
Say
914.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 947. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works