Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete

Precoated/mill finish aluminium Crimp curve
Item number
12.66.5
Analysis basis
21.412 sqm
Priced inputs
8
Derived rate
₹914.70/ METRE
D-01/RATE ANALYSISITEM 12.66.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.66.5 (Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium Crimp curve) is derived from 8 priced inputs for 21.412 sqm and works out to ₹914.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • crimp curve 20.2 metres long complete
  • length and 1.06 metre wide
  • Area 20.20 x 1.06 = 21.412 sqm + Add wastage @ 5% = 1.071 sqm. Total = 22.483 sqm.
ANALYSIS OF RATES · ITEM 12.66.5DETAILS OF COST FOR 21.412 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3072MATPrecoated/Mill finish Aluminium crimp curvesqm22.48554.0012,455.58
3074MATStainless steel self tapping screw of 6x50mm with SS hex cap and 3mm thick EPDM sealStainless steel self tapping screw of 6x50 mm with SS hex cap and 3 mm thick EPDM seal100 Nos0.4511.00204.40
9977MATCarriage of screws, washers and curvesL.S.9.882.2722.43
9999MATSundriesL.S.6.242.2714.16
OTHERLABOUR——0.00
0130LABMistryday0.1897.0089.70
0112LABCarpenter 2nd classday0.3816.00244.80
0114LABBeldarday1736.00736.00
BUILD-UP TO RATE
Total
13,767.07
Add 1 % Water charges on “W”
+137.67
TOTAL
13,904.74
Add GST on “X” (multiplying factor 0.2127)
+2,957.54
TOTAL
16,862.28
Add 15% CPOH on “Y”
+2,529.34
TOTAL
19,391.62
Add Cess @ 1% on “Z”
+193.92
Cost of 21.412 metre
19,585.54
Cost of 1 metre
914.70
SAY
₹914.70
D-02/SOURCEPRINTED PAGE 947
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
947

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 947. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.