Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete

Precoated/mill finish aluminium Gutter (600 mm over all girth)
Item number
12.66.6
Analysis basis
Detail of cost of 100 metre
Priced inputs
14
Derived rate
₹1,808.65/ METRE
D-01/RATE ANALYSISITEM 12.66.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.66.6 (Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium Gutter (600 mm over all girth)) is derived from 14 priced inputs and works out to ₹1,808.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 0.63mm thick with zinc coating not less than
  • 275gm/ sqm
  • Consider a length of 100m
ANALYSIS OF RATES · ITEM 12.66.6DETAIL OF COST OF 100 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3073MATPrecoated/Mill finish Aluminium guttermetre100736.0073,600.00
9977MATCarriage of gutterL.S.10.42.2723.61
1008MATFlats upto 10 mm in thicknessFlats up to 10 mm in thicknessquintal0.7495,450.004,082.05
3074MATStainless steel self tapping screw of 6x50mm with SS hex cap and 3mm thick EPDM sealStainless steel self tapping screw of 6x50 mm with SS hex cap and 3 mm thick EPDM seal100 Nos2511.001,022.00
3076MATStainless steel bolts & nuts 10 mm dia and 125 mm long round head with slotseach30041.0012,300.00
9977MATCarriage of screws, seam bolts & washerL.S.27.32.2761.97
9999MATSundriesL.S.53.32.27120.99
0102LABBlacksmith 1st classday5897.004,485.00
0114LABBeldarday5736.003,680.00
9999MATSundriesL.S.126.12.27286.25
0130LABMistryday2.8897.002,511.60
0102LABBlacksmith 1st classday8.4897.007,534.80
0112LABCarpenter 2nd classday6.2816.005,059.20
0114LABBeldarday16.8736.0012,364.80
BUILD-UP TO RATE
Total
1,27,132.27
Add 1 % Water charges on “W”
+1,271.32
TOTAL
1,28,403.59
Add GST on “X” (multiplying factor 0.2127)
+27,311.44
TOTAL
1,55,715.03
Add 15% CPOH on “Y”
+23,357.25
TOTAL
1,79,072.28
Add Cess @ 1% on “Z”
+1,790.72
Cost of 100 metre
1,80,863.00
Cost of 1 metre
1,808.63
SAY
₹1,808.65
D-02/SOURCEPRINTED PAGE 948
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
948

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 948. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.