Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete

Precoated/mill finish aluminium Gutter (600 mm over all girth)

Item number
12.66.6
Analysis basis
Detail of cost of 100 metre
Priced inputs
14
Derived rate
1,808.65 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.66.6 Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium Gutter (600 mm over all girth) — is derived from 14 priced inputs and works out to ₹1,808.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 0.63mm thick with zinc coating not less than
  • 275gm/ sqm
  • Consider a length of 100m
CodeInputUnitQuantityRate (INR)Amount (INR)
3073Precoated/Mill finish Aluminium gutterMaterialmetre100736.0073,600.00
9977Carriage of gutterMaterialL.S.10.42.2723.61
1008Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterialquintal0.7495,450.004,082.05
3074Stainless steel self tapping screw of 6x50mm with SS hex cap and 3mm thick EPDM sealStainless steel self tapping screw of 6x50 mm with SS hex cap and 3 mm thick EPDM sealMaterial100 Nos2511.001,022.00
3076Stainless steel bolts & nuts 10 mm dia and 125 mm long round head with slotsMaterialeach30041.0012,300.00
9977Carriage of screws, seam bolts & washerMaterialL.S.27.32.2761.97
9999SundriesMaterialL.S.53.32.27120.99
0102Blacksmith 1st classLabourday5897.004,485.00
0114BeldarLabourday5736.003,680.00
9999SundriesMaterialL.S.126.12.27286.25
0130MistryLabourday2.8897.002,511.60
0102Blacksmith 1st classLabourday8.4897.007,534.80
0112Carpenter 2nd classLabourday6.2816.005,059.20
0114BeldarLabourday16.8736.0012,364.80
Total
1,27,132.27
Add 1 % Water charges on “W”
1,271.32
TOTAL
1,28,403.59
Add GST on “X” (multiplying factor 0.2127)
27,311.44
TOTAL
1,55,715.03
Add 15% CPOH on “Y”
23,357.25
TOTAL
1,79,072.28
Add Cess @ 1% on “Z”
1,790.72
Cost of 100 metre
1,80,863.00
Cost of 1 metre
1,808.63
Say
1,808.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 948. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.