Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete

Precoated/mill finish aluminium Barge board (Upto 200 mm)

Item number
12.66.4
Analysis basis
Details of cost for 8.23 metres Completed
Priced inputs
9
Derived rate
813.25 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.66.4 Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium Barge board (Upto 200 mm) — is derived from 9 priced inputs for 8.23 metres and works out to ₹813.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • length of barge boards
  • length of barge boards = 8.23 metre + Add
  • wastage @ 5% = 0.41 metre. Total = 8.64
  • metre
CodeInputUnitQuantityRate (INR)Amount (INR)
3071Precoated/mill finish aluminium Barge board (Upto 200 mm)Materialmetre8.64493.004,259.52
0222Seam bolts and nuts 6 mm dia and 25 mm longMaterial10 Nos0.511.005.50
1211Washer for seam boltsG.I. plain washer for seam boltsMaterial100 Nos0.132.003.20
3075EPDM washerMaterial100 Nos0.541.0020.50
9977Carriage of barge boards, bolts, nuts and washersMaterialL.S.9.362.2721.25
9999SundriesMaterialL.S.6.762.2715.35
0130MistryLabourday0.04897.0035.88
0112Carpenter 2nd classLabourday0.06816.0048.96
0114BeldarLabourday0.4736.00294.40
Total
4,704.56
Add 1 % Water charges on “W”
47.05
TOTAL
4,751.61
Add GST on “X” (multiplying factor 0.2127)
1,010.67
TOTAL
5,762.28
Add 15% CPOH on “Y”
864.34
TOTAL
6,626.62
Add Cess @ 1% on “Z”
66.27
Cost of 8.23 metre
6,692.89
Cost of 1 metre
813.23
Say
813.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 947. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.